[Halld-cal] Notes of Bcal Readout meeting 7/15/2010
Elton Smith
elton at jlab.org
Fri Jul 16 14:17:03 EDT 2010
Minutes of the Bcal Readout meeting have been posted on the wiki and
copied here for easy access.
Attendees: Fernando, Elton, Yi, Eugene, Beni, Chuck, Tim, John (JLab);
Andrei (UofR); Alam, Will (USM)
# Announcements
#* USM has shipped signed MOU via TNT Express, should arrive later this
week.
#* USM connected using ESnet and voice communication was excellent. (ESnet
dropped out once at the JLab end but unrelated to USM connection).
# Review of Action Items
# Update - USM
#* No report
#* Statement of work is now needed to be worked out in detail. It needs to
be accompanied by a Fasttrack Schedule with milestones. Will to revisit
early draft and update for next meeting.
# Simulation runs
#* Simulation of cosmic-ray runs are ongoing and will be ready in time to
analyze data.
# Cosmic-ray setup at UofR
#* 3rd point completed, will add 2 more points and repeat measurement at
center of module.
#* Measurements take long time to accumulate the data and are being
impacted by power outages in Regina
#* Overall spectra look reasonable and roughly scale by anticipated
factors.
#* Extraction of the npe/MeV numbers will require careful analysis and
checks of data quality.
# Geometry
# [[SiPM Radiation Hardness Test]] (Update from Yi)
#* 1x1 and 3x3 mm2 samples were intially tested by Carl and are now being
irradiated by the AmBe neutron source from Radcon.
#* Ji has updated his web links to reflect latest calculations by Pavel
and his interpretation of those calculations.
# Light guides
Elton Smith
Jefferson Lab MS 12H5
12000 Jefferson Ave
Suite # 16
Newport News, VA 23606
elton at jlab.org
(757) 269-7625
(757) 269-6331 fax
More information about the Halld-cal
mailing list