Hi Elton:
A great BRAVO to all people involved in this success, at JLab, Athens and USM! We're looking so forward to the actual signals from electrons in the mini-cal!
George
>>> Elton Smith 03/23/12 5:11 PM >>>
Dear collaborators,
We reached another milestone today. The SiPMs, cooling plate, electronic
boards were assembled into two units for installation onto the
mini-Bcal. The response of all SiPMs in the assemblies were checked for
appropriate analog and TDC outputs. Some problems were found on each
module. Fernando and Chris debugged the dead channels, finding some
shorted cables and a design flaw on the board layout. After fixing these
issues the assemblies were retested and found to have correct signals on
all outputs.
The replacement "K" light guide arrived from Santa Maria yesterday and
was glued onto the Bcal module today. The control board from Athens
arrived earlier this week and was also installed onto the mini-Bcal.
Some photos can be found on the wiki at
https://halldweb1.jlab.org/wiki/index.php/BCAL_Beam_Tests_2012#Photos_and_Plots
Next week we will start hooking up the ectype to the electronics and
connecting up to the DAQ.
Cheers, Elton.
--
Elton Smith
Jefferson Lab MS 12H5
12000 Jefferson Ave
Suite #16
Newport News, VA 23606
(757) 269-7625
(757) 269-6331 fax
_______________________________________________
Halld-cal mailing list
Halld-cal at jlab.org
https://mailman.jlab.org/mailman/listinfo/halld-cal
More information about the Halld-cal
mailing list