Nick,
I checked the configuration file for the linear stages of the goniometer.
Although the XPS boards can provide 3A, we run these two stages with
0.2A peak current
and we keep them at rest with holding current of 0.1A .
Hovanes.
On 6/26/19 4:53 PM, Hovanes Egiyan wrote:
> Hi,
>
> Let's have a Hall D controls meeting on, Thursday, June 27 at
> 10:00am in CEBAF Center B101. I posted the preliminary agenda on the
> wiki page:
>
> https://halldweb1.jlab.org/wiki/index.php/Controls_Meeting_27-Jun-2019
>
> Feel free to add more topics for discussion to the agenda.
> The meeting is in B101 in the B-wing of CEBAF Center.
>
> Best,
> Hovanes
>