<html>
  <head>
    <meta content="text/html; charset=ISO-8859-1"
      http-equiv="Content-Type">
  </head>
  <body bgcolor="#FFFFFF" text="#000000">
    <div class="moz-cite-prefix">Hi, <br>
      <br>
      I posted the minutes of the controls meeting on the wiki page:<br>
      <br>
<a class="moz-txt-link-freetext" href="https://halldweb1.jlab.org/wiki/index.php/Controls_Meeting_8-Jan-2015#Minutes">https://halldweb1.jlab.org/wiki/index.php/Controls_Meeting_8-Jan-2015#Minutes</a><br>
      <br>
      and also pasted them below. <br>
      <br>
      Best, <br>
      &nbsp;&nbsp;&nbsp; Hovanes. <br>
      <br>
      <br>
      <h2><span class="mw-headline" id="Minutes">Minutes </span></h2>
      <p>Present: Dave, Mark, Scot, Hovanes
      </p>
      <h4><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=3"
            title="Edit section: Announcements">edit</a>]</span> <span
          class="mw-headline" id="Announcements"> Announcements</span></h4>
      <ul>
        <li> Yi will be leaving at the end of January. Hall D group
          needs to learn the slow controls subsystem that Yi has
          developed. Dave and Brian are looking into the PXI system for
          the solenoid. </li>
      </ul>
      <h4><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=4"
            title="Edit section: Gas system">edit</a>]</span> <span
          class="mw-headline" id="Gas_system"> Gas system </span></h4>
      <ul>
        <li> Dave will be working on the gas system controls. Namely he
          will implement the communications between PLC and the Brooks
          controllers to be able to set the most parameters in the
          controller downstairs from PLC. We would like to be able to
          change the flow or to completely shut off the valves in the
          MFC in the hall from the hall. </li>
        <li> Dave also suggested to have a NC solenoid valve for each
          FDC package so that we do not need to rely on the serial
          communications in case of emergency. It was pointed out that
          this is something that may trigger a review, the FDC group
          needs to make decisions on that.
        </li>
      </ul>
      <h4><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=5"
            title="Edit section: Remote reset of CAENs">edit</a>]</span>
        <span class="mw-headline" id="Remote_reset_of_CAENs"> Remote
          reset of CAENs </span></h4>
      <ul>
        <li> Dave have plans for redoing the remote reset for CAENs
          without using 5V output modules that currently kill the HV
          from CAEN each time PLC is rebooted. </li>
        <li> This may require additional purchases of PLC equipment,
          Hovanes will ask Eugene about POA.
        </li>
      </ul>
      <h4><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=6"
            title="Edit section: Warm magnet power supplies">edit</a>]</span>
        <span class="mw-headline" id="Warm_magnet_power_supplies"> Warm
          magnet power supplies </span></h4>
      <ul>
        <li> The procedures for TAG5C and SWEEP magnet ramping require
          approching the desired setpoint from above after staying near
          the saturation point for a while. </li>
        <li> During the fall run we had incidents for both PS and tagger
          where the magnet currents were not raised to the <b>maximum</b>
          values before putting them at the nominal setpoint. </li>
        <li> Accelerator magnets approach their desired setpoints from
          below after looping multiple times for degaussing, so the
          existing software does not accommodate TAG5C and SWEEP, but
          probably can be modified to execute our simple loop. </li>
        <li> Hovanes will talk to Gary about making such changes.
        </li>
      </ul>
      <h3><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=7"
            title="Edit section: Solenoid controls work">edit</a>]</span>
        <span class="mw-headline" id="Solenoid_controls_work"> Solenoid
          controls work </span></h3>
      <ul>
        <li> Mark would like to have the correct time maintained on the
          solenoid power supply. He thinks the precision might be
          limited to 1sec by the power supply, but he will be check
          that. </li>
        <li> Dave is planning to implement some mechanism by which the
          time will be transferred from PLC to the power supply either
          periodically or upon some condition being satisfied. He would
          like to have a PLC tag connected to EPICS that reports a
          correct time. </li>
        <li> Hovanes suggested to use the time from EPICS/PLC interface
          IOC for the solenoid. He will send Dave the name of the tag,
          and Dave will take care of the conversion. Hovanes will also
          see if the server on which the production version of that IOC
          is running can be synced with JLab time servers. </li>
        <li> Flow meters for the leads will be replaced by Scot. </li>
        <li> Dave is considering a possibility of being able to stop a
          slow dump and ramping PS back to the setpoint. This might not
          be so easy, if not impossible, to do without going to the fast
          dump, according to Mark. </li>
        <li> New liquid level sensor will be installed and needs to be
          integrated with the controls system.
        </li>
        <li> Monitoring circuit for GFD is being worked on by Mark. </li>
      </ul>
      <h4><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=8"
            title="Edit section: More alarms">edit</a>]</span> <span
          class="mw-headline" id="More_alarms"> More alarms </span></h4>
      <ul>
        <li> Mark will send Hovanes a list of LCW quantities which will
          be useful to have in the magnet section of the Hall D alarm
          system. </li>
        <li> Scot suggested to have the hall humidities and temperatures
          in the alarm system as well. Hovanes will add them.
        </li>
      </ul>
      <h4><span class="editsection">[<a
href="https://halldweb1.jlab.org/wiki/index.php?title=Controls_Meeting_8-Jan-2015&amp;action=edit&amp;section=9"
            title="Edit section: Other items">edit</a>]</span> <span
          class="mw-headline" id="Other_items"> Other items </span></h4>
      <ul>
        <li> Two more motors will probably be installed for April
          running: beam profiler in front of the collimator and the
          polarimeter target in front of the east wall of the collimator
          cave. </li>
        <li> The specs for the polarimeter target motion system is still
          not well known, the details are coming in. </li>
        <li> The stage for the beam profiler is being designed, the
          cabling is expected to be very similar to collimator and
          harps. </li>
        <li> Target controls by the JLAB target group is pretty much
          done. They implemented the target controls in compact-RIO, but
          have an EPICS CA-server (or IOC) to interface it with Hall D
          EPICS. The target group needs a Windows PC in the counting
          house. we can share the halldsc7 that Dave is using for PLC
          with them. Hovanes will setup a meeting with the target group
          to work out the details of integration.
        </li>
        <li> Scot reminded us that TAC motor needs to be tested. It has
          been locked-out/tagged-out during the last fall running.
          Hovanes will get together and check that the TAC stage is
          fine.
        </li>
      </ul>
      <br>
      <br>
      On 01/07/2015 09:48 AM, Hovanes Egiyan wrote:<br>
    </div>
    <blockquote cite="mid:54AD4745.9020409@gmail.com" type="cite">Happy
      New Year,
      <br>
      <br>
      We should restart having our regular Hall D controls meetings this
      week.
      <br>
      We will have our Hall D&nbsp; slow controls meeting on January 8, 2015,
      <br>
      at 9:30am in A110. I posted the preliminary agenda on the wiki
      page:
      <br>
      <br>
<a class="moz-txt-link-freetext" href="https://halldweb1.jlab.org/wiki/index.php/Controls_Meeting_8-Jan-2015">https://halldweb1.jlab.org/wiki/index.php/Controls_Meeting_8-Jan-2015</a>
      <br>
      <br>
      The main topics of the meeting will be short updates on what each
      of
      <br>
      us is working or will be working for the April engineering run.
      <br>
      Please, feel free to add your topics for discussion to the agenda.
      <br>
      <br>
      Hovanes.
      <br>
    </blockquote>
    <br>
  </body>
</html>