First shipment of MWPCs received!


------------------------------------
Elton Smith
Jefferson Lab MS 12H3
12000 Jefferson Ave STE 4
Newport News, VA 23606
(757)269-7625

Begin forwarded message:

From: elton at jlab.org<mailto:elton at jlab.org>
Subject: [Revised Logentry] First shipment of MWPCs delivered
Date: June 9, 2021 at 11:55:01 AM EDT
To: elton at jlab.org<mailto:elton at jlab.org>, stevensm at jlab.org<mailto:stevensm at jlab.org>, whitey at jlab.org<mailto:whitey at jlab.org>, zihlmann at jlab.org<mailto:zihlmann at jlab.org>

First shipment of MWPCs delivered<https://logbooks.jlab.org/entry/3879603>

  *   Edit<https://logbooks.jlab.org/entry/3879603/edit?destination=email/send>
  *   Delete<https://logbooks.jlab.org/entry/3879603/delete?destination=email/send>

Lognumber 3879603<https://logbooks.jlab.org/entry/3879603>. Submitted by elton<https://logbooks.jlab.org/user/elton> on Wed, 06/09/2021 - 11:37<https://logbooks.jlab.org/entries?start_date=1623249474&end_date=1623256674&book=HDFMWPC>.
Last updated on Wed, 06/09/2021 - 11:52
Logbooks:       HDFMWPC<https://logbooks.jlab.org/book/hdfmwpc>

  *   Rory drove the first 4 MWPCs for the CPP experiment down from UMass yesterday.
  *   The U-Haul truck with the shipment was at the lab before 9 am.
  *   Mark S. assembled his crew. Rory gave instructions on how to re-attache the wheels to the MWPCs and they were rolled off the truck and into EEL 126
  *   The unloading was performed safely with no incidents due to careful planning. All MWPCs were unloaded in about 30 min.
  *   All 4 chambers, the HV system and hardware are stored in EEL 126.
  *   The foam pads used during transport are also in the same room. They will be collected and shipped back to UMass for transport of the reamining 4 chambers.
  *   Christian Whalen and Martha Eakins from property were shown the equipment so it could be properly inventoried.
  *   Beni is coordinating the test setup by preparing an OSP, setting up gas supply with Scot Spiegel, and assessing LV and HV connections with Chris Stanislav.

[https://logbooks.jlab.org/files/styles/plentybig/public/2021/06/3879603/Unload1.png]
[https://logbooks.jlab.org/files/styles/plentybig/public/2021/06/3879603/Unload2.png]
[https://logbooks.jlab.org/files/styles/plentybig/public/2021/06/3879603/Unload3.png]
[https://logbooks.jlab.org/files/styles/plentybig/public/2021/06/3879603/Unload4.png]

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-cpp/attachments/20210609/3e46b146/attachment.html>


More information about the Halld-cpp mailing list