[Halld-jlab] Hall D Staff Meeting notes, June 20, 2011

Mark M. Ito marki at jlab.org
Tue Jun 21 11:57:46 EDT 2011


Find the notes at 
http://www.jlab.org/Hall-D/software/wiki/index.php/Private:Hall_D_Staff_Meeting%2C_June_20%2C_2011 
and as text below.

   ==

Private:Hall D Staff Meeting, June 20, 2011

    Present: Fernando Barbosa, George Biallas, Eugene Chudakov (chair),
    Hovanes Egiyan, Mark Ito, David Lawrence, Bert Manzlak, Lubomir
    Pentchev, Elton Smith, Simon Taylor, Tim Whitlatch, Elliott Wolin, Beni
    Zihlmann

Eugene

      * Raises
           + there was a freeze, but some room for Lab to give small raises
           + raises to those hired before June 2010, size small, tuned by
             management according to their rules, 0.5 to 2.0%
      * IT review
           + Mark gave presentation
           + recommendations not wrong, they reviewed whether our
             requirements are reasonable
           + Hall D is new, tracking in our geometry unexplored,
             fundamental uncertainty larger for D than for B
           + committee didn't see enough structure in code development
           + Eugene: no coordination with physics goals
                o vertical coordination missing
           + lots of optimism from IT about providing resources
           + but...what if estimates are off? 20%? 30%?
      * New hire
           + 30 applications for new physicist position, we could use help
             now
           + committee: Eugene, Glenn Young, Elton, Tim, John Domingo,
             Brian Moffitt
           + will look for 2nd candidate at the same time
                o hire next fiscal year
                o interest in GlueX physics important, possible role in
                  coordination of data analysis
           + some letters not quite in yet, want to finish first cut this
             week(?)
      * there are office space issues
           + Cody got office near hovanes
           + new physicst will share with cody


Elton

      * Two visitors from MIT coming Wednesday
           + they will work on conceptual design for replacement solenoid
           + Elton wants to talk to George, Tim, and Elliott about a
             schedule for them
           + George: drawings?
      * BCAL project has been going well
           + exchange rate with the looney on par with dollar, caused
             over-run of 300 k$ to cover currency fluctuation, though 50 k$
             of actual overrun
           + very little rejection of fibers
                o for little cost will build another module, Project OK
                  with cost
                o PR goes in today
      * Eugene: status of read-out?
           + mechanical, prototype pieces have been purchased at 8 times an
             affordable cost
           + electrical, 1st design for whole thing, finding issues, boards
             have been put together, rise time too slow, unclear what
             solution will be
           + want to start ordering production components this fall
             according to schedule
           + Eugene: can it be delayed? Elton: would like not to have
             schedule slip
      * design issue, granularity of the read-out
           + summing scheme matters, but initial results are not fully
             trusted yet
           + additional material impacts efficiency, in region of last
             plane of FDC's, material coming from electronics mechanical
             support and cooling
           + George: EHS&Q's Bruce Lenzer an expert on functional analysis
                o what are critical areas
                o am I paying for things that are in fact critical?


Bert

      * Conflict with Hall C meeting, Bert and Javier will cover both C and
        D meetings
      * Bert is our point of contact for safety
      * Elton: Paul Collins's relationship to Hall D?
           + right now things being done here generally go to Bert
      * Tom Carsten's concern via George: is there a standard OSP for
        Physics about man-lifts
           + Bert: one is going around now
           + addresses platforms, rails, harnesses, fitting of harnesses,
             approved tie-off points, tie-off strength in pounds per person
           + look out for sharpshooters
      * construction area had a recordable injury
           + stepped off one working surface to another, twisted ankle
           + person given restrictions


Lubomir

      * testing first cell, tomorrow move to EEL 126
      * problem cannot use source at Blue Crab
           + Bert: no RCA at Blue Crab ever
           + Radcon says no, but more discussion will be held
           + transporting a button source "beyond scope of the license"
           + consistent with previous story that that we cannot use source
             off-site
      * second cell is almost ready
           + Chris Stanislav did good job populating PCB's, would be happy
             to have him for further work
      * third cell: technicians are working on it
      * for second cell, need to clean wire frame, will clean with alcohol
      * HV on first cell OK except for 1 sector, 2100 V on others
           + have all channels working except one
      * for second cell, plan is to start assembling it
           + do not have gusset ring for both sides of package
           + option: use empty frame for now, but risk damage when
             disassemble and re-assemble with proper part
      * size of dead area of chamber: need decided now, may start with
        smallest dead circle size
           + Sascha Somov has calculated size: 2.7 cm radius for first
             package
      * problem wih AC, temerature was increased from 69 to 72 F
           + humidity went from 45 to 54%
           + has been put back


Simon

      * working on simulation of FDC response
           + make more realistic by putting in clusters
           + also simulate electronics response
      * working on for CDC as well as FDC
           + working on magnetic field and Lorentz force effect
           + drift time depends on magnetic field
                o from 1.5 to 2.(?) Tesla, 50-50 mixture shows 10's of ns
                  difference in drift time
                o 90-10 mixture: effect is large, 100 ns or so


Tim

      * installation meeting this morning
           + revitalize discussion of cabling of FDC, CDC
           + not looked at for two years, tooling of installation depends
             on this
           + decided to make mechanical mock-up, BCAL cables, FCAL, CDC,
             FDC too
      * Hall D access
      * there is a COO for Hall D, please to back and read it
           + must access through accelerator site now
           + call Tom before you start work and get his approval
           + if work going on with construction, need long pants as well as
             other PPE, e. g., hard hat
           + if you drive through construction site and get out of vehicle
             there, need full Ballard PPE
      * upstream platform bids by Thu.(?)
      * grouting of rails for FCAL platform ready to go(?)


Elliott

      * almost have agreement with DAQ group on support tasks
           + simulated evio output file
           + event builder
           + dis-entangler
      * crates and rates study
           + need Dave need to get the right rate
      * controls meeting
           + gas system P&I presented
           + SiPM cooling P&I an unknown
      * setting up control equipment in (?) with Hovanes
      * task for undergraduate
           + Eugene: field vs. current, lag, eddy currents
      * Dmitry Romanov is back
      * coil test
           + coil 2 is going great
           + pumping and purging, mechanical stuff is done
           + no leaks so far
           + perhaps cool as early as next week
           + Cody working in Danfysik
           + thinking of getting Danfysik to work on platform a year from
             now, coordinating with other Halls
           + question: one or two quench protection channels?


George

      * yesterday, pumping on helium circuit, lot of water was absorbed by
        Micarta
           + cannot do a good leak test, put in some current to heat things
             up
           + over weekend had a cryogenic volume filled with nitrogen,
             warmed up, when opened this morning water at the bottom
      * have not been able to detect any leaks so far
      * leaks between cryocan and coil, internal to system
      * see 10^-6 standard cc of He per second, want 10^-9
      * Jonathan Creel came back from cryogenic conference, a lot of
        interest in poster from people who had worked on LASS magnet
           + when integrated over several decades, a pretty large community
             apparently
      * bids for filler rings and BCAL supports came in at 167 k$, just
        about right
           + a good vendor: made all dipoles and yokes and assemblies for
             CEBAF
      * do we need racks to be moved to below 50 Gauss or can we increase
        the cladding? Tim consulting with Floyd Martin on this
      * Wayne(?) now doing drawing for platform around magnet
           + are we going to fill space with Cerenkov counter? if so we
             need to leave room in platform design
           + consensus: please leave space for a Cerenkov counter
      * safety item: troughs in Hall are uneven, a footing hazard


Hovanes

      * playing with Beni's flow controller
           + a good sandbox for evaluating control system
           + CSS display manager, looks good
      * PC104 computers
           + ran an IOC, control module
           + pxc booting linux system
                o Sasha and Brian put up a tftp server
                o changed it to used halld group disk area (M drive)
                o each readout controller needs access to this area
      * got 5 vme cpu's, ordered in march, looked different from Sergey's
           + have not been booted yet
      * room 126 is ready, racks are there, can put modules in, there is an
        HV and a VXS crate in that room
           + chassis for PLC, make a test stand, Beni's gas system(?)
                o make a gas panel for testing
                o Elliott: will need Windows computer for Allan Bradley
                  software, or not


Beni

      * implemented simulation for geometry of BCAL read-out with material
        for cooling of SiPM's
           + try to calculate efficiency for photons in the gap
           + goal: turn-key code system to generate efficiencies as
             function of energy and angle
           + extra material may not be as bad as long light guides


Fernando

      * Cody Dickover started last week
           + from FEL
           + helped with solenoid power supply, he will start with that
           + that PS came from Hall A, radiation damage suspicion
      * talked to Scot Spiegel, ready from electronics standpoint for ???
      * personnel: lots of applications for 2nd technician
      * if you have requests, send needs, and how long it will take, to
        Fernando
      * procurements:
           + LVPS systems, at procurement
           + cables at procurement, finance part needs to checking off
      * Naomi tested ABD HV board
           + ready to go into production, need 149, will order 160
      * pre-amp cards: working on to sending to Procurement
      * these procurements run out the money for this year
      * bcal read-out
           + electronics on a board, 1 in. or 2 from SiPM
           + U-board attached to mechanical piece
           + two cables that bias and takes signals
           + electronics works, impedance of the cable is the problem
           + 16 cells being read, high capacitance
           + any additional resistance or inductance in series degrades the
             rise time
           + if reactance is significant, see an increase in rise time
                o important for timing: part of signal goes to
                  discriminator
                o other part goes to adc
           + do not have resolution to measure such small ???.
           + did calculations, inductance of 100-120 nH
           + ran simulations, got exactly results seen in lab
           + two options
                o if timing is important, two components
                     # fast rise time, 15 ns is the spec
                     # keep pulse widths below 80 ns, 100 in spec to
                       Hamamatsu
                     # can compensate to decrease rise time
                     # or decrease the length of the cable
                     # if done at the ?? should be fine
                     # see if one (?) is feasible, ask Jim Fochtman
                     # Beni: is cliping an option? Fernando: would like to
                       stay away from shaping
                     # still doing careful measurements should have a
                       document this week and move forward
                o if we cannot decrease length of the cable that much, move
                  preamp from the preamp board to the uboard, that resolves
                  both issues completely, but raises thermal issues
      * Eugene: plans for Cody? Fernando: we have lots of instrumentation
        (?)
           + test preamp
           + test ASIC's, but actually Fernando will do this
                o we will have ASIC's next week
           + develop testing infrastructure for preamp
                o would be nice to do automated tests
                o if not, do checks
           + flash 125 interface with Gerard
           + testing of the tdc's
                o student from UMass here to get started with flash 250's
                o idea is to get him fully trained
           + Hovanes control system will need help with boxes
           + Elliott: with the new technician, the more he nows about
             controls the better
                o Fernando, if you have a request for work let me know in
                  advance so work can be scheduled
                o brought job description: job is a II
                o if you have a requirement let me know
           + technicians will be used where needed
           + Chris Stanislav: Fernando talks to him everyday, wants to put
             a hold on him, restrict projects he works on
           + Cody has experience with electronics


David

      * looking at event size
           + problem with hdgeant: crashes when adding beam-induced
             electromagnetic background
      * resolutions: getting things correct in smearing
      * documentation of source code
           + so that non-familiars can work with code
      * Eugene: BCAL summing, time-scale? Dave: when do you want it?
        segmentation answers in next month should be do-able
           + Elton: fine and course segmentation comparison the issue
                o energy resolution not far off
                o position resolution, related to timing, more complicated,
                  need more sophistication in simulation.
           + Eugene: benefit from help from others? Dave: hard to say
           + Elton: Andrei and Irina also working on this
           + Fernando: right now in the 334, if no further issues, we are
             in good shape
                o if additional 8 channels, especially on inner part,
                  problematic for electronics
                o if answer ready in a month changes can be accomodated


Mark

      * request for more work space, 7 TB -> 30 TB
      * elected to User Group Board of Directors, computing responsibilties
      * start counter: leaning toward FMPMT's
      * MOU's
           + FIU about to go into concurrence chain
           + UMass in concurrence chain

    Retrieved from
    