[Halld-jlab] Hall D Staff Meeting Notes, April 9, 2012
Mark M. Ito
marki at jlab.org
Tue Apr 10 12:47:32 EDT 2012
Hall D'ers,
Find the notes at
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_April_9,_2012
and below.
-- Mark
_____
Private:Hall D Staff Meeting, April 9, 2012
Present: Eugene Chudakov (chair), Kwame' Coles, Hovanes Egiyan, Mark
Ito, Vanik Kakoyan, David Lawrence, Lubomir Pentchev, Simon Taylor, Tim
Whitlatch, Elliott Wolin, Glenn Young, Beni Zihlmann
Installation, Tim
* installation schedule made with an eye toward the accelerator
schedule
+ Tom Carstens has a detailed schedule
+ Eugene with post schedule on Hall D page
* pair spectrometer magnet pole pieces in, there was a fit problem,
fixed
* tagger magnet: by this week company should be winding coils
* downstream platform awarded for about half of expected price
* cryogenic platform: facilities is reviewing design
* tagger vacuum chamber: materials ordered
* beamline components: finalization underway with Sascha
+ Tom has a list of things to order
+ some pair converter details yet to be decided
* tooling for BCAL: half way welded up, should be done by end of
month
* stands for tagger magnet: PR issued
* shims installed in magnet, between yokes
* baffle supports: design done, tooling done
* design for BCAL rails near final
* electrical work in counting house: UPS to be installed today or
tomorrow
* there is backup plan to put plugs into counter-sunk bolt holes in
pair spectrometer magnet if they affect the field
* breakthrough from accelerator tunnel to Hall D beamline will be
done during 16-month shutdown
* sag in photon beamline is still there will be forever; should not
be a problem
* tagger power supply becomes available in May
+ Giles talking to Bill Merz about spare parts, etc.
+ 480 V available in service building to plug it in
* Radiated noise concern from Fernando:
+ as for UPS requirements in Hall, need to create a list
+ some class A devices, e. g., network switches
* Giles can sign control circuit diagrams, he will let us know if he
is not comfortable with any such assignments
Flash 125, Cody
* a prototype flash 125 came in last week
+ boards for main and mezzanine
+ some parts need to be replaced, resistors
+ should be assembled in next couple of days
+ will be programmed and tested
+ Beni would like to get one
+ want to test pulser out
+ test vectors need to be written
* working with Procurement on main order
FDC Construction, Lubomir
* assembled first refurbished cell on Thu., started flushing with gas
* oxygen level drops over days, one cell per week, leveled out at 900
PPM
* looks like May to finish the package, unless test rate increased
* the testing chamber, got to 300 PPM, 3 O-rings
* expect higher level with 5 O-rings
* getting leakage, garden variety, tighten, dropped to 570 PPM
* harder O-rings susceptible to leakage compared to old ones
* leakage similar to what was seen in prototype
Software Review Preparations, David
* Friday meetings continue
* chair for review committee identified, not announced
* organizers are working on the schedule
* charge has not been circulated
* meeting tomorrow on preparations for review
+ slides prepared on areas of concern
* research management document: not clear if that is relevant
* talk outlines are due in two weeks
* first dry run May 14 or 15
* review will be June 7 and 8
* activity list coming along, some feedback coming in
BCAL Test, Eugene
* mini-BCAL has been connected, in the beam, signals were captured
* heat issue
+ from electronics to SiPM plate
+ heats up by 5 degrees C when electronics turned on
+ perhaps insulation between plates not enough
+ heat path not yet understood
* range of signals with electrons measured
+ first impression: signals too big
+ with 1 GeV electrons, some channels go to 1/2 of full range
* some electronics issues, oscillations
Retrieved from