[Halld-jlab] Hall D Staff Meeting Notes, May 20, 2013

Mark M. Ito marki at jlab.org
Tue May 21 13:19:58 EDT 2013


Find the notes at 
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_May_20,_2013 
and below.
   _________________________________

Private:Hall D Staff Meeting, May 20, 2013

    Present: Eugene Chudakov (chair), Hovanes Egiyan, Nerses Gevorgyan,
    Mark Ito, David Lawrence, Lubomir Pentchev, Yi Qiang, Sascha Somov,
    Simon Taylor, Elliott Wolin, Beni Zihlmann

Eugene

      * Jonathan delivered 1st dewar to cool magnet
      * scare last week, voltage taps were shorted
           + turned out due to jumpers added in resistor box to accommodate
             individual coil differences while testing in Test Lab
           + quench detector was affected
           + jumpers removed now, nominal impedances seen.
           + nothing is shorted inside the magnet
      * end of this week or beginning of next, magnet should be full
      * analysis being done with respect to SLAC measurements of short
        samples
           + they put short samples in magnetic field, look for quench
           + ran at 1600 amps
           + 4.5 K at SLAC, 4.6 K here
           + looks like we were far from critical current
      * have to test magnet up to 140 A
      * find any turn-to-turn shorts
      * high power test: parameters not decided, schedule not set
      * two week cycle to warm refrigerator and clean
           + requires a couple of days down since magnet stays pretty cold

Beni

      * Working on TAC report for the PAC, report due tomorrow, almost done

David

      * working intensively on simulation for pion polarizability
           + added muon detector to private version of simulation
      * translation tables: have spreadsheet to database to XML conversions
        automated

Yi

      * working on solenoid
      * chasing shorts
           + resolving problem with jumpers on back of resister box
           + with all jumpers removed, no shorts
           + identified short to ground between coils 3a and 3bc, 17 ohms,
             we saw this before
      * working with Carlos preparing partial wave analysis test data set
      * we may split BaBar DIRC bars with PANDA

Simon

      * looking at what happens if we at 1200 A
           + full simulation, will look at effect on resolution and
             kinematic fitting
      * for DIRC, need to know angular resolution on face of DIRC, study in
        progress
      * added improvement in track finding in CDC
      * studying overall efficiency for tracking
           + some tracks do not have good chi-squared
           + tricky issue, tuning track recovery code
           + working on alignment procedure

Elliott

      * finished with build/release/version-control system, packages build
        OK now
           + missing one scripts comes from offline
           + releases can be made
      * Sergey Pozdnyakov will work on inventory system
      * in case we go to a new quench detector, looking at designs,
        candidates identified

Sascha

      * working on simulation for eta decays
      * trigger
           + two crate system in F117, with 2 CTPs, several flashes in each
             crate
           + added SSP last week
           + playback being used to exercise system
           + checked synchronization
           + looking at scalers with Roman
           + GTP should come in tomorrow, from Scott K.
           + TS is with Dave A. now
           + 3rd crate in hand
      * beamline
           + meeting with Vladimir P. and Bill Crahen on amps and dividers
             for fixed array, checking physical fit
                o will order PCBs soon
           + Bill in touch with Franz and Dan on support structure
      * more than 60 pair spectrometer tiles done out of 290
           + ordered another fixture, Anatoly gluing pretty fast now
           + measuring tiles as they are done
      * in touch with Richard [engineer?] on mounting frame for low and
        high granularity counters
           + will have two separate stands
      * PMTs for fixed array have arrived
      * support structure for microscope
           + cooling design rehashed
      * CTP scaler document sent to Fast Electronics Group
           + three energy thresholds
      * Hovanes: want all modules reporting to EPICS
      * flash adc scalers, being used for beam test[?]
      * server situation[?]: Roman wrote prototype of shared memory server
      * document for hit patterns[?]

Lubomir

      * crew working on 2nd cell of spare package
           + trips from time to time
           + opened twice so far, fixed some problems, old wire frames
             being used
           + last two problems due to bad soldering, wires sticking out
           + localized problem now
      * cannot use SMC chiller using Flourinert, tried two water chillers,
        one more powerful than the other
           + looks like SMC chiller, just to run it, produces significant
             heat internally
           + some misunderstanding possible
           + Bill C. in contact with experts from company
           + will delay test with full electronics, unless we can use tap
             water for SMC
      * worked on simulation of Cherenkov light in lead glass
           + relevant for trigger for pion polarizability
           + tried varying parameters, may be difficult to simulate light
             collection, there is uncertainty in surface roughness
           + apparent energy peak (shower equivalent) from muons traveling
             along bar can vary from two to three times actual energy loss
           + used parameters for GAMS experiment, they tuned them with
             measurement with muons

Mark

      * TOF
           + sending splitters to FSU
           + Kathleen in touch with FSU on invoicing
           + readiness review report submitted
      * Offline
           + helped with proposal preparation, computing requirements
           + forum for PWA analysis open, uses Drupal
           + new tagged release: 2013-04-22
           + started thinking about next data challenge
      * Start Counter
           + sending discriminators to FIU
           + contract awarded for FIU start counter construction
                o previously: submitted review of technical proposal
      * UMass electronic testing: sent out message waiving the readiness
        review for TDC testing

Hovanes

      * procurements
           + PO issued for servers for database, etc.
                o mounting adapters still missing
           + ordering desktop computers for cubicles, signed but not
             ordered
           + 10 Gb transceivers for network being ordered
                o switches were ordered, without transceivers,
           + ordering 4 scaler modules, Struck, for beam profiler and for
             active collimator
           + VME CPU PR in system
                o shortage right now, just have the ones we have already
                  loaned to DA group
           + no word or Chip Watson purchase of monitoring farm, EMUs,
             infiniband
      * EPICS
           + installing gateway to export variables to outside world
           + some issues with running EPICS and ROC on same VME controller
                o old issue
                o resolved, related to locking of VME bus, two processed
                  can now access bus
           + implementing scaler read-out for FADC

Nerses

      * working on HV and LV systems: GUI, archiving
           + looking at Beni's GUIs
           + physical vs. logical channel naming info will come from a
             database

    Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_May_20,_2013"

-- 
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295



More information about the Halld-jlab mailing list