[Halld-jlab] Hall D Staff Meeting Notes, February 24, 2014
Mark Ito
marki at jlab.org
Thu Feb 27 13:32:23 EST 2014
Folks,
Find the notes at
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_February_24,_2014
and below.
-- Mark
_____________________________________________________________________
Present:
Present: Eugene Chudakov (chair), Mark Dalton, Alexandre Deur, Hovanes
Egiyan, Sergey Furletov, Mark Ito, David Lawrence, Lubomir Pentchev,
Sergey Pozdniakov, Dmitry Romanov, Elton Smith, Sascha Somov, Simon
Taylor, Tim Whitlatch, Glenn Young, Beni Zihlmann
=Eugene=
* we need to speed up rate of claiming progress
** we increased the number of FTEs by 3
** we met to streamline list of online activities
* review coming in mid-March
** we need to submit a plan for commissioning
** will have to explain why some installations delayed
** need to update dates of activities
** officially everything needs to be installed by the end of the project
=Sascha=
* working on BCAL read-out
** coda configuration, translation tables, XML file
** continue with BCAL, reading out crates
** pulser in TI
** Sergey: 2 master TIs
** transceiver for slave TI, not yet done
** 5 extra transceivers
* trigger crates read this or next week
** just have to move crates
* data with external pulser, FCAL
** this week maybe LED
* implementing configuration files
** then read-out F1-TDC
** configuration file, Sergey working on it
* CTP, FCAL cosmics
** trigger from trigger supervisor, read-out 1 BCAL or 2 BCAL or 1 FCAL
* pair spectrometer counters: almost fabricated one arm
** cannot check, box procurement delayed, March 10
* did dose distribution in tagger hall
=David=
* translations tables, written in XML, now stored in CCDB
** updated plug-in that reads it
** updated plugin that goes the other way
* re-captured data from latest version of Fernando's spreadsheet
** entered into CCDB
* worked on EVIO output from a split ROC
** running coda 3.0.1 on a virtual machine
** 2 ROCs
** example: enable merging of events streams onto disk
* identified AFECS bug
** fed back to DAQ group
* working to overcome difficulty getting run number from the CODA system
* will do Gluon file system clean-up soon
* hdview2 work to view single tracks
** Beni had a solution, will adopt it
* PyEPICS installed on gluon cluster
=Tim=
* manpower added
** Joe Beaufait working with us
** ACC electricians installed new circuit box in gas shed
** pair spectrometer power supply getting hooked up now
** still need more electrical help
** contract engineer position on hold
* TOF support structure issue resolved
* air system progress: documentation
* gas system
** tanks came in
** still paperwork to do
* BCAL cooling system progressing
* design of TAC and installation plan done
* photon beamline to dump progressing
* goniometer stand grouted, vacuum chamber going in
* microscope support and shielding box design done
* tagger window will be formed tomorrow
* pair spectrometer mapping mechanical set-up done
** next: polarity, hi-pot tests
** will try to get help with this
** still need requirements
* CDC HV connections be re-worked: Slava and Beni are on it
* foam came in for start counter; drawings to machine shop next week
* Facilities installed flammable gas detection system
* BCAL cooling: pressure and leak tested, waiting on power for chillers
=Hovanes=
* working on FCAL EPICS HV control
** prototype exists
** fitting into scheme developed by Vanik and Nerses
* Nerses due here on March 10
* procurements
** aluminum radiators: 10<sup>-3</sup>, 10<sup>-4</sup>, 10<sup>-5</sup>
** six phones for Hall
** Dave Butler put in some PLC system orders
* PSS system installs started in Counting House
** speaker, status display, crash buttons
* ordered 2 computers to install in Hall
** Sergey ordered stands for these
* power outage in Hall last Saturday
** brought systems up on Sunday
** main network switch was off, cannot control CAEN supplies in that state
=Eugene=
* George Biallas installed relief valve for top of magnet, replaces
rupture disk
* studying a safer exhaust system for helium, pipe goes to the edge of
crane, not a lot of room
=Lubomir=
* FDC: done testing and fixing wires using Beni's min-DAQ
** 50% of test done
** tested cathodes with scope
** two cables need fixing
** 1 24-channel F1-TDC is noisy on the output (no spares)
* Cathodes: Cody and Beni working on them
** waiting for that work to finish before testing
** then fixing
** then chamber insertion
* Fast shutdown: chiller status broken
=Alexandre=
* working on pair spectrometer mapping
** OSP
** need requirements
** wants to self-train on software program to control probes
* commissioning target
** met with Matt Marchlik
** will call a meeting for this week [added in press: the meeting will
be at 3:30 pm, Thu., Feb. 27, in F228]
=Mark I.=
* continue work on data challenge
** new tag over the weekend
** submitted jobs against it
** success rate higher; not quantified yet
* badge rack in counting room
** meeting 9 am Monday in CH with Becky
*** Hovanes, Tom, and Mark I.
*** she is busy with week with audits of RadCon
** give Becky a list of move candidates
*** she checks if they have a radiation badge
*** if so, she contacts them to see if they want to move
*** no move happens without confirmation from the individual
* Collaboration email list moved to JLab
** Security concerns at IU
** Sherman White of CNI helped us with that
* Bruce Lenzer will visit Eljen
** travel planned anyway
* JANA/CLARA meeting was held
* Hall D group list updated nightly as CCDB authors
=Simon=
* preparing of for offline data challenge
* continuing work on alignment
** able to reproduce artificially introduced shifts
=Mark D.=
* putting single board computers into crates
** DHCP, DNS for all BCAL, FDC, FCAL
* BCAL ready for cosmics
=Elton=
* waiting to work on BCAL
** temperature readout: 2 RTDs not working
* pulser system: wiring mistake on control board
* FCAL remake cables, BCAL remake distribution boards
=Sergey F.=
* planning to look at how to have different subsystems can run DAQ in
the Hall in parallel
=Beni=
* Last week, ADC read-out showed every 56th event corrupted
** number of samples hand coded in more than one place
** will make it a parameter of firmware
** can read at 6 Hz only; needs fixing
* CDC read-out
** 2 CMU students here
** some cosmic data taking done
** goal: get data for alignment
* gas system
** Ar gas racks next to gas shed now
** CO2: not yet
** mass flow controllers are back from the company
** O2 gas analyzer working, on cart in Hall
=Eugene=
* We have a new Installation Coordinator: Mark Dalton
--
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295
More information about the Halld-jlab
mailing list