[Halld-jlab] Hall D Staff Meeting Notes, May 19, 2014
Mark M. Ito
marki at jlab.org
Thu May 22 15:03:55 EDT 2014
Folks,
Find the notes below and at
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_May_19,_2014
.
-- Mark
____________________________________________________________
Present: Eugene Chudakov (chair), Mark Dalton, Alexandre Deur, Hovanes
Egiyan, Sergey Furletov, Nerses Gevorgyan, Mark Ito, Vanik Kakoyan,
David Lawrence, Lubomir Pentchev, Sergey Pozdniakov, Yi Qiang, Elton
Smith, Sascha Somov, Simon Taylor, Glenn Young, Tim Whitlatch, Beni
Zihlmann
=Eugene=
* office move
** check furniture in new office, make sure not removed
** resources: Walk Akers, Rachel Harris
** Alexandre: take phone with you and extension will not have to be changed
** offices for users: submitted a list to Lorelei, some have been
reserved already
* students must have a JLab supervisor even if working mainly with a
university adviser
* special PAC
** assign additional priority to already approved experiments
** 600 hours total to be assigned
* open house
** attendance down a bit from past years
* collaboration meeting
** good to see detector signals read out
=Tim=
* target
** being assembled on card
** gas system almost there, 90%
** Dave Butler and Werth Teachey working on controls
** on track for June test in EEL
* start counter
** Rohacell being machined, flats going on now
** hubs made, test fit with target, test fit with electronics, all OK
* electrical power
** almost there in Hall
** tagger hall done
** UPS: Joe B. working on it
* pair spectrometer: stand for detectors installed
* thin windows for beamline going in
* commissioning target: designed, pieces on order
* flammable gas detector system on order
* chamber gas system
** pressure relief valve due in tomorrow
** certification from vendor on manifold did not come, will go another way
=David=
* attempted CODA configuration with 32 crates: issues
* 14 crate set-up ran during open house
* next: farm manager
=Alexandre=
* target review last week
* ion chamber in tagger hall, provision for 2 locations being discussed
=Sergey P.=
* board installation updates in DB
* TI boards, no spares, enough master
* 53 TIs altogether
* Sascha: Chris will buy more, < 2 k$ each
* FADC 250: 5 in repair
* TOF crate ready for test
** CAEN TDCs checked with external clock
* 2 new computers in Hall
** FCAL, BCAL north
* improvements in DB
** new features
** hints for appropriate configuration actions
* config file for F125
** working on a file
** set look back, DAC values
=Sascha=
* BCAL trigger, no GTB, SSP only, issues
** started looking at GTP
* CDC and FDC crates, will read-out this week
* Beni wants TD* Hai finalizing scalars for CTP
* optical fibers from UConn with scintillator arrived
** visually look good
** Anatoly working on collimator for source
** will do single pixel calibration
** called St. Gobain
=Simon=
* commissioning target in Monte Carlo now
* issues with ghost tracks: one source in track finding in FDC found and
fixed
* time-to-distance in CDC going into reconstruction
=Mark I.=
* SRM fixes
** certificates needed refresh
* halldweb1 upgrade
** clean-up db and web applications
* ccdb 1.0 released
* ubuntu 14 build for gluex software released
* workflow meeting with scicomp
** workflow tools: development starts
** write-through cache: plans being made
=Hovanes=
* gas systems: Mike S., Dave B. made presentation at controls meeting
* BCAL temperatures available in EPICS, needs GUI
* parameters from VME chassis added to EPICS
* archiving with accelerator archiver: BCAL temps, VME PS temps
* network configuration for gluon machines: some moved to control network
* FCAL driver for HV control: still working on it
* Manuel will do gui and SQLite DB for IOC configuration
* Vanik and Nerses working on TOF HV control, almost ready
=Lubomir=
* FDC waiting for gas system
* progress on alignment and calibration methods
** 6 parameters per cell
** resolution improves with use of constants
=Mark D.=
* BCAL pedestals, gains, timing: analyzing all of these
=Elton=
* finished looking at north side of BCAL, 2 SiPM signals missing
** will go to the south side
* next TDCs, cosmics
* readiness review
** beginning of July
** instructions to shift takers
*** do it on wiki
*** not for experts, turn on, turn off, etc.
** readiness for detectors
*** checklists need to be composed
*** controls and online will need sections
=Yi=
* solenoid
** variable resistor to balance quench detector installed
** discussion of checklists and procedures started
** Wed.: meet with Danfysik
** more work on solenoid gui
* DIRC: list of resource for 1st year testing being compiled
=Beni=
* gas bottle connected to CDC
** safety bubbler OK
** 300 cc/min, 40/60 mixture (Ar/CO2)
* DAQ under development
=Sergey F.=
* working on start-up, monitoring procedure
=Vanik=
* they are installing fiber to tagger hall