[Halld-jlab] Hall D Staff Meeting Notes, September 22, 2014
Mark Ito
marki at jlab.org
Tue Sep 23 20:47:54 EDT 2014
Folks,
Find the notes below and at
https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_September_22,_2014
.
-- Mark
__________________________________
Private:Hall D Staff Meeting, September 22, 2014
From GlueXWiki
Present: Vladimir Berdnikov, Eugene Chudakov (chair), Mark Dalton,
Alexandre Deur, Hovanes Egiyan, Sergey Furletov, Mark Ito, Lubomir
Pentchev, Serguei Pozdniakov, Yi Qiang, Elton Smith, Sascha Somov, Simon
Taylor
Project End, Eugene
* Outstanding activity is the diamond radiator
o 80 k$ left for FY14, 50 k$ for FY15
o Needs to be done by March
* Flash 125: 400 k$ obligated
* Reviews:
o Director's Review Nov. 4
o Final DOE Review: Nov. 18-20
* Last progress report due Sep. 29
o Activities may only be extended if work by other groups is the
cause of delay, if then
* Let Eugene know of any other purchases we need to make against 12
GeV now.
o Elton to reset MPOD crates: PDU's, 10 needed, about $200 each
Run Preparations, Elton
Hot Check-Out
Assignments are as follows:
System Responsible Person
Beam Alexandre
Controls Hovanes
DAQ Sergey F.
Detector various
Electronics Fernando Barbosa
Mechanical Tom Carstens
Online no checklist
Solenoid George Biallas
Trigger Sascha
Cell Phones
* Cell phones have been distributed to the groups
* We need a scheme to distribute on-call work equitably around the
collaboration
Data Acquisition, Sergey F.
* The three new nodes have come in. We will run with them.
* Elton suggested over-the-weekend runs with a global trigger and
global data acquisition as a near-term goal
* Eugene: need for simulation to have estimate of various detector and
trigger rates. Simon: this is an active effort
Shift Check-List
Alexandre showed the first draft. Comments welcome. See the
commissioning wiki.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_September_22,_2014"
* This page was last modified on 24 September 2014, at 00:44.
--
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-jlab/attachments/20140923/9c9c09b0/attachment.html
More information about the Halld-jlab
mailing list