Present: Vladimir Berdnikov, Eugene Chudakov (chair), Mark Dalton, 
Alexandre Deur, Hovanes Egiyan, Sergey Furletov, Mark Ito, Lubomir 
Pentchev, Serguei Pozdniakov, Yi Qiang, Elton Smith, Sascha Somov, Simon 
Taylor


  Project End, Eugene

  * Outstanding activity is the diamond radiator
      o 80 k$ left for FY14, 50 k$ for FY15
      o Needs to be done by March
  * Flash 125: 400 k$ obligated
  * Reviews:
      o Director's Review Nov. 4
      o Final DOE Review: Nov. 18-20
  * Last progress report due Sep. 29
      o Activities may only be extended if work by other groups is the
        cause of delay, if then
  * Let Eugene know of any other purchases we need to make against 12
    GeV now.
      o Elton to reset MPOD crates: PDU's, 10 needed, about $200 each


  Run Preparations, Elton


    Hot Check-Out

Assignments are as follows:

System 	Responsible Person
Beam 	Alexandre
Controls 	Hovanes
DAQ 	Sergey F.
Detector 	various
Electronics 	Fernando Barbosa
Mechanical 	Tom Carstens
Online 	no checklist
Solenoid 	George Biallas
Trigger 	Sascha


    Cell Phones

  * Cell phones have been distributed to the groups
  * We need a scheme to distribute on-call work equitably around the
    collaboration


  Data Acquisition, Sergey F.

  * The three new nodes have come in. We will run with them.
  * Elton suggested over-the-weekend runs with a global trigger and
    global data acquisition as a near-term goal
  * Eugene: need for simulation to have estimate of various detector and
    trigger rates. Simon: this is an active effort


  Shift Check-List

Alexandre showed the first draft. Comments welcome. See the 
commissioning wiki.

Retrieved from 
"https://halldweb1.jlab.org/wiki/index.php/Private:Hall_D_Staff_Meeting,_September_22,_2014"

  * This page was last modified on 24 September 2014, at 00:44.


-- 
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295

-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-jlab/attachments/20140923/9c9c09b0/attachment.html 


More information about the Halld-jlab mailing list