Fernando,
Thanks for the list. I will add these tasks to to overall schedule
for this opening (and add any others as they come up).
Two comments:
1. I hope that you can get the work done on the CDC sooner than
3/27/15 as the CRYO Target will need to be installed around the first
week of March so it can be hooked-up/run up/tested/aligned/installed by
the end of the month.
2. What is MO?
regards,
Tom
On 1/5/2015 2:00 PM, Fernando J Barbosa wrote:
> Hi all,
>
> There are a number of tasks related to the electronics in the hall
> that we will be addressing before the next run in April. I attach an
> Excel file with preliminary information. Please review and provide
> feedback such as additional requests, details, etc.
>
> Thanks and best regards,
> Fernando
>
>
> _______________________________________________
> Halld-jlab mailing list
> Halld-jlab at jlab.org
> https://mailman.jlab.org/mailman/listinfo/halld-jlab
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-jlab/attachments/20150105/1c2ceb2d/attachment.html
More information about the Halld-jlab
mailing list