Private:Hall D Staff Meeting, September 28, 2009 Present: Fernando Barbosa, George Biallas, John Domingo, Eugene Chudakov, Chuck Hutton, Mark Ito, David Lawrence, Slava Razmyslovich, Sascha Somov, Elton Smith, Simon Taylor, Beni Zihlmann Eugene * Recommendations from the Lehman Review for Hall D 1. Management team: should look more like the other Halls, an electrical engineer should be added to the team o Elton: committee wants to see a procedure for deciding technical issues 2. solenoid, options: 1. build a new one 2. continue to refurbish old one and prepare to build a new one 3. continue to refurbish o Eugene: Need a program to evaluate these options, probabilities of failure, implications of these failures o Elton: form a committee, designate a chairperson to get evaluation moving 3. preference expressed for FMPMT's over SiPM's, January deadline for decision 4. re-evaluate manpower, especially university contributed o Eugene: this is mostly software, PWA cannot be in a construction project * In six months there will be another review, not known if it will be a full oneor not Dan * Continuing work on full-scale prototype * procedure for soldering rigid flex boards being specified * wire planes being cleaned as part of program to find source of high current draw Beni * working on the FDC test stand, effort to reproduce Simon's results on small prototype * cathodes look good, 500 micron resolution Fernando * pre-amp assembled outside by outside vendor, testing, works well * ASIC does not meet requirements, preliminary + gains should be twice GAS1 for cathodes and 1/3 for anodes + anode gain a bit higher than form GAS1 + linearity very bad + power consumption ok + discriminator section works, but only without planned back termination on output + Mitch has to go back to the drawing board, pre-amps in February, probably * Elton: flash adc's schedule need re-evaluation David * position dependent position resolution put in * FCAL smearing moved from dana to mcsmear * further rootspy program work done * note and study for mapping magnetic field + magnitude of difference between nominal and perturbed changes FDC fields by 2%. rho meson mass doed not reflect this change at the expected level George * coil 1 being capped up, some cracks in tack welds on clips * statement of work for coil 3 started * coil 2 work (?) * Tom will start on yoke pieces * test stand still in review * may not need to order new u-tubes * discussion on nature of potential shorts due to stainless steel rings at the inner windings of the coils Chuck * updating FDC model and drawings * working with George and Floyd on magnet drawings Slava * ground between aluminum plate and connectors generating issues * layout of HV board needs modification because of leads for grounding * location of holes depends on width of boards * need to add 175 holes to endplate Sascha * simulation work on tagger magnet, can make it narrower by 5-7 cm * checking rate for microscope counter, looks like about 3 to 5 MHz Simon * work on tracking, especially multi-particle final states * dE/dx particle ID in CDC working well for low momentum particles Elton * working on simulation of light guides for fine-mesh pmt's, confirming USM design and simulation work * future design effort will be required for this system Retrieved from "http://www.jlab.org/Hall-D/software/wiki/index.php/Private:Hall_D_Staff_Meeting%2C_September_28%2C_2009"