    <div class="moz-cite-prefix">Hi all,<br>
      <br>
      Expect the electronics to be off during the week of June 15th (see
      below email from Tim). All the electronics in the hall and tagger
      will be turned off by COB on 6/12 (Friday); turn on will occur on
      6/22 (Monday) and as follows:<br>
      <br>
      a) all VXS and VME crates will be turned on and will remain on
      indefinitely (request by David L.)<br>
      b) all CAEN and MPOD chassis will remain off until beam operations
      re-start. Please, send me scheduling requests.<br>
      <br>
      Best regards,<br>
      Fernando<br>
      <br>
      <br>
      <br>
      <br>
      <br>
      On 5/29/2015 11:35 AM, Timothy Whitlatch wrote:<br>
    </div>
    <blockquote
      cite="mid:1981512859.2317191.1432913750395.JavaMail.zimbra@jlab.org"
      type="cite">
      <div style="font-family: arial,helvetica,sans-serif; font-size:
        12pt; color: #000000">
        <div>Hi All,<br>
        </div>
        <div><br data-mce-bogus="1">
        </div>
        <div>There is a planned power outage for Hall D scheduled the
          week of June 15th.<br data-mce-bogus="1">
        </div>
        <div>There will be 2 outages;<br data-mce-bogus="1">
        </div>
        <div>The first is a 4 hour period where only items on UPS will
          remain under power.<br data-mce-bogus="1">
        </div>
        <div>The second is a 2-3 day outage that will have a generator
          installed to power critical items in the Hall, counting house
          and cryo building..<br data-mce-bogus="1">
        </div>
        <div><br data-mce-bogus="1">
        </div>
        <div>There will be no air conditioning in the Hall, counting
          house or Tagger for these periods.<br data-mce-bogus="1">
        </div>
        <div><br data-mce-bogus="1">
        </div>
        <div>Please have all equipment turned off prior to this.<br
            data-mce-bogus="1">
        </div>
        <div><br data-mce-bogus="1">
        </div>
        <div>If there is something that requires power during this
          period, please contact Tom Carstens as he is organizing the
          generator powered circuits.<br data-mce-bogus="1">
        </div>
        <div><br data-mce-bogus="1">
        </div>
        <div>I will update with exact dates as I find out.<br
            data-mce-bogus="1">
        </div>
        <div><br data-mce-bogus="1">
        </div>
        <div>Cheers,<br data-mce-bogus="1">
        </div>
        <div><br>
        </div>
        <div data-marker="__SIG_PRE__">Tim Whitlatch<br>
          Hall D Engineer<br>
          Jefferson Lab<br>
          600 KELVIN DR STE 5<br>
          Newport News, VA 23606-4468 <br>
          757-269-5087</div>
      </div>
      <br>
      <fieldset class="mimeAttachmentHeader"></fieldset>
      <br>
      <pre wrap="">_______________________________________________
Halld-jlab mailing list
<a class="moz-txt-link-abbreviated" href="mailto:Halld-jlab@jlab.org">Halld-jlab@jlab.org</a>