<html>
  <head>

    <meta http-equiv="content-type" content="text/html; charset=UTF-8">
  </head>
  <body>
    <p>Folks,</p>
    <p>Please find the notes <a moz-do-not-send="true"
href="https://halldweb.jlab.org/wiki-private/index.php/Hall_D_Staff_Meeting,_November_9,_2020">here</a>
      and below.</p>
    <p>  -- Mark</p>
    <p>________________________________________________________</p>
    <p> </p>
    <div id="content" class="mw-body" role="main">
      <h1 id="firstHeading" class="firstHeading" lang="en"><span
          dir="auto">Hall D Staff Meeting, November 9, 2020</span></h1>
      <div id="bodyContent" class="mw-body-content">
        <div id="mw-content-text" dir="ltr" class="mw-content-ltr"
          lang="en">
          <p>Present: Alexander Austregesilo, Eugene Chudakov (chair),
            Mark Dalton, Alexandre Deur, Sergey Furletov, Mark Ito, Igal
            Jaegle, Keigo Mizutani, Lubomir Pentchev, Patrizia Rossi,
            Sascha Somov, Simon Taylor, Tim Whitlatch, Beni Zihlmann
          </p>
          <h2><span class="mw-headline" id="Announcements.2C_Eugene">Announcements,
              Eugene</span></h2>
          <ul>
            <li> There will be an All-Hands Meeting on Nov 17.</li>
            <li> Appraisals go to the next stage, one-on-one meetings,
              starting this week.</li>
            <li> SAD progress
              <ul>
                <li> spare cold compressor removed, will go back to Oak
                  Ridge</li>
                <li> roughly on schedule</li>
              </ul>
            </li>
            <li> DOE Long-Range Plan process will start at the beginning
              of next year</li>
            <li> Meetings with Bob McKeown to assess progress in hybrid
              search</li>
            <li> Hall D staff may have to perform calibrations for SRC</li>
          </ul>
          <h2><span class="mw-headline" id="Engineering.2C_Tim">Engineering,
              Tim</span></h2>
          <ul>
            <li> Tagger spectrometer going back together
              <ul>
                <li> waiting for survey and alignment</li>
              </ul>
            </li>
            <li> hardening systems:
              <ul>
                <li> vacuum</li>
                <li> nitrogen flow</li>
              </ul>
            </li>
            <li> DIRC mirrors biggest item on the books</li>
            <li> Setting up the CPP experiment
              <ul>
                <li> on cusp of finalizing design of support frame, then
                  on to procurement</li>
              </ul>
            </li>
          </ul>
          <h2><span class="mw-headline" id="Other_News.2C_Eugene">Other
              News, Eugene</span></h2>
          <ul>
            <li> 25% tariffs were levied on crystals from China, funds
              to cover being sought</li>
            <li> EIC project: collecting "letters of intent" from
              various institutions, including those from other countries</li>
          </ul>