[Halld-level1] [New Logentry] CTP Boards are Ready to install back to the Hall
sergpozd at jlab.org
sergpozd at jlab.org
Wed Aug 20 17:40:02 EDT 2014
Logentry Text:
--
CTP Boards are Ready to install back to the Hall.
Is it a good time to do it tomorrow morning, till lunch time ?
Regards, Serguei P.
On 08/20/2014 02:32 PM, Jeff Wilson wrote:
> Hi Sergey, The CTP boards have been cleaned and are ready for pickup in the Electronics' group
> lab. You can drop off some more at your convenience. Jeff
>
>
> Boards that have been completed. Boards need to be entered into the PEER application.
> CTPV2-002
> CTPV2-004
> CTPV2-007
> CTPV2-011
> CTPV2-012
> CTPV2-015
> CTPV2-016
> CTPV2-017
> CTPV2-019
> CTPV2-021
> CTPV2-022
> CTPV2-025
> CTPV2-026
> CTPV2-029
> CTPV2-030
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/3291753
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-level1/attachments/20140820/89ee7297/attachment-0002.html>
More information about the Halld-level1
mailing list