[Halld-offline] Offline Software Meeting Minutes, August 3, 2016
Mark Ito
marki at jlab.org
Thu Aug 4 11:23:25 EDT 2016
Folks,
Find the minutes below and at https://goo.gl/MsDKJA .
-- Mark
_____________________
GlueX Offline Meeting, August 3, 2016, Minutes
Present:
* *CMU*: Naomi Jarvis, Curtis Meyer
* *IU*: Matt Shepherd
* *JLab*: Alexander Austregesilo, Amber Boehnlein, Mark Ito (chair),
Paul Mattione, Nathan Sparks, Justin Stevens, Simon Taylor, Beni
Zihlmann
* *MIT*: Maria Patsyuk, Cristiano Fanelli
* *NU*: Sean Dobbs
* *Regina*: Tegan Beattie
You can view a recording of this meeting <https://bluejeans.com/s/a6NJ/>
on the BlueJeans site.
Announcements
1. *Database Server upgrade: 5.5.50-MariaDB*. The upgrade was complete
successfully
<https://halldweb.jlab.org/talks/2016/db_upgrade_2016-07-21.pdf> two
weeks ago by Marty Wise of CNI.
2. *sim-recon-2.2.1*. This sub-minor release
<https://mailman.jlab.org/pipermail/halld-offline/2016-July/002427.html>
fixes the double-free bug for the 2.2 branch. This is now being used
by sim1.1.
3. *Analysis TTree: Unused Tracks/Showers No Longer Saved*. By default,
unused hypotheses are not longer saved
<https://mailman.jlab.org/pipermail/halld-offline/2016-July/002425.html>
in particle combos. The old behavior can be recovered by setting an
argument to the tree-output-enabling function. This results in a 40%
reduction in disk space for the recent Analysis Launch.
Review of minutes from the last meeting
We went over the minutes from the meeting on July 20
<https://halldweb.jlab.org/wiki/index.php/GlueX_Offline_Meeting,_July_20,_2016#Minutes>.
* *Managing Plugins*. We agreed that, at least in the short term, we
should pursue options 2 and 3 from the list:
o 2. Reduce the number of plugins that are built automatically.
(Justin)
o 3. Have finer-grained build targets for SCons so that parts of
the build can be skipped depending on the needs of the user. (Sean)
* *Bad files in Lustre*. Mark and Alex have reported a few more bad
files resulting in lost data. Alex has seen files go bad since the
Lustre upgrade.
Report from SciComp Meeting on July 21
Mark reviewed the agenda from the meeting
<https://halldweb.jlab.org/talks/2016/scicomp_2016-07-21.pdf>.
* We are getting 48 new farm nodes, with 18 cores each, and 190 TB of
disk.
* A software review is coming in November.
* There may be an overlap between a planned down of the tape library
and Hall D running.
At this SciComp meeting Mark brought up the idea of charging for memory
usage in the fairshare algorithm. It is a scarce resource; often times
cores go idle because a farm node cannot accommodate more jobs due to
memory. There was some discussion of how this could be done.
With multi-threaded JANA jobs memory usage vis-a-vis CPU usage is
efficient. Curtis remarked that we have put a lot of effort into
optimizing resource usage. It was a huge commitment on our part and all
groups should take that seriously across the Lab.
Report from Computing Round Table on August 2
Mark reported in the meeting held yesterday
<https://halldweb.jlab.org/talks/2016/round_table_2016-08-02.pdf>. Wes
Bethel <http://vis.lbl.gov/%7Ewes/> from LBNL described an ASCR workshop
he organized that addressed data challenges faced by Office of Science
experimental and observational science programs.
In the morning before the meeting, Wes met separately with each of the
Halls. We presented brief overviews of our computing model and mentioned
"pain points" that we are feeling. Mark, Justin, Alex, and Sean
participated in the Hall D session.
Amber made some remarks:
* She solicited input on speakers and topics that might be presented
at these meetings. Four have been held so far. Amber can often come
up with a name from outside the Lab to address a specific topic, and
speakers from inside the Lab are sought as well.
* Wes's slides are available <https://www.jlab.org/indico/event/157>
on the Lab's Indico site.
* Wes has noticed similarities in problems faced in programs across
the Office of Science programs, yet the discussion at any one lab
tends to emphasize differences.
* She thinks that computing is a frontier area for the 12 GeV program.
In this context, specifically in the areas of data management,
computational science, and visualization, we should look to learn
from others whenever possible.
* Mark will announce future meetings to the offline group. Folks
should feel free to participate when topics stimulate personal interest.
Analysis Launch
Alex described the Analysis Launch. It started last week and included
contributions from 12 people. In all 46 channels were analyzed. The jobs
are finishing now. There was some competition from sim1.1 otherwise
things would have gone faster. In all there are 4 TB of ROOT trees and
another 1 TB of ROOT histograms.
Alex led us through the Analysis Launch section (near bottom) of the
launch analysis webpage
<https://halldweb.jlab.org/data_monitoring/launch_analysis/index.html>.
The link there shows various statistics and graphs of the jobs
<https://halldweb.jlab.org/data_monitoring/analysis/summary_swif_output_analysis_2016-02_ver01_batch01.html>.
Next Monitoring Launch
Sean proposed that if the new tracking code is ready we should try
another monitoring launch to test those and other improvements to the
code. Simon thinks that the code is ready. We decided to try to do a
launch this Friday.
On a related note, folks thought that the time is right for Mark to do
another sim-recon release.
sim1.1
Mark reported on the [sim1_1 jproj status, 8-3-16|status] of sim1.1
<https://halldweb.jlab.org/gluex_simulations/sim1.1/>. 75% off the jobs
and most of the resulting REST files have been written to tape.
Justin suggested running an analysis launch on the sim1.1 REST files. We
endorsed the idea, but did not find a volunteer.
ROOT 6 Upgrade?
We discussed several points, but in the end agreed on the following course:
* For now we keep ROOT 5 as the default version.
* We maintain a parallel build of all packages against ROOT 6. Early
adopters can try this out.
* We run the next monitoring launch using the ROOT 6 version as a
large scale test.
* The assumption is that all of our public compiled code is compatible
with both versions of ROOT. If that turns out not to be true, then
the scheme breaks down.
* Not all macros (they do not participate in the build procedure) will
be compatible with both versions and so people running those will
have to know what they are doing. Since the default remains ROOT 5,
old macros will continue to work for the naive user.
* Once we have established that using ROOT 6 in the monitoring launch
is working, we will revisit the issue.
Review of recent pull requests
We reviewed the list of recent pull requests
<https://github.com/JeffersonLab/sim-recon/pulls?q=is%3Apr+is%3Aclosed>.
We mainly expressed shock and awe at the large number of commits in
Simon's recent upgrade of the tracking code
<https://github.com/JeffersonLab/sim-recon/pull/489> to include timing
information from the FDC anode wires. Corresponding changes to the CCDB
have been entered.
Review of recent discussion on the GlueX Software Help List
We looked over recent conversations
<https://groups.google.com/forum/#%21forum/gluex-software>.
Maria has got the ROOT visualization of the detector
<https://groups.google.com/forum/#%21topic/gluex-software/cGfeCq6G8aA>
going, though there are some features left to be desired. Simon
mentioned that the hdgeant++ (CERNLIB) programs has tools that are
useful for finding overlaps and the like.
Retrieved from
"https://halldweb.jlab.org/wiki/index.php?title=GlueX_Offline_Meeting,_August_3,_2016&oldid=76654"
* This page was last modified on 4 August 2016, at 11:20.
--
marki at jlab.org, (757)269-5295
-------------- next part --------------