[Halld-online] [Halld-level1] [New Logentry] CTP Boards are Ready to install back to the Hall

Alexander Somov somov at jlab.org
Thu Aug 21 12:18:39 EDT 2014


Hi Sergei,

Please go ahead with the installation. Let's do it today.

Cheers,
        Alex



On Wed, 20 Aug 2014, sergpozd at jlab.org wrote:

>
> Logentry Text:
> --
>
> CTP Boards are Ready to install back to the Hall.
>
>
> Is it a good time to do it tomorrow morning, till lunch time ?
>
>
> Regards, Serguei P.
>
>
> On 08/20/2014 02:32 PM, Jeff Wilson wrote:
>
>>      Hi Sergey, The CTP boards have been cleaned and are ready for pickup in the Electronics' group
>> lab. You can drop off some more at your convenience.  Jeff
>>
>>
>> Boards that have been completed. Boards need to be entered into the PEER application.
>> CTPV2-002
>> CTPV2-004
>> CTPV2-007
>> CTPV2-011
>> CTPV2-012
>> CTPV2-015
>> CTPV2-016
>> CTPV2-017
>> CTPV2-019
>> CTPV2-021
>> CTPV2-022
>> CTPV2-025
>> CTPV2-026
>> CTPV2-029
>> CTPV2-030
>
>
>
> ---
>
> This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3291753