[Halld-pid] Minutes, Time-of-Flight Meeting, January 19, 2012
Mark M. Ito
marki at jlab.org
Thu Jan 19 15:49:56 EST 2012
Folks,
Find the minutes at
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_January_19,_2012#Minutes
and below.
-- Mark
_____
GlueX TOF Meeting, January 19, 2012
Minutes
Present:
* FSU: Paul Eugenio, Sasha Ostrovidov
* JLab: Eugene Chudakov, Chuck Hutton, Mark Ito (chair), Tim
Whitlatch, Beni Zihlmann
Phototube Purchase
Beni reviewed [20]the proposal he floated last month along with [21]the
subsequent discussion on the email list (see the items in the "PMT
choice for TOF" thread). We agreed that, all things considered, we
should go ahead an adopt his proposal and initiate the purchase of the
ten-stage tubes for the entire array. Some things we need to bear in
mind:
* Eugene suggested that we have amplifier ready if needed (see
"subsequent discussion").
* We still want to test eight-stage tubes. FSU has a couple of these
and will pursue these tests.
* We want to have a mechanical design that allows replacement of
tubes in the high-rate area with reasonable effort during a
shutdown period.
Mark will initiate writing of the PR.
Mechanical Design
This morning there was a phone conference to discuss issues with the
light guides for the half-width counters. Present were Paul Eugenio,
Kurt Koetz, Randall Smith, and Ian Winger at FSU and Chuck Hutton at
JLab. They agreed on:
* adding 1 cm flat sections, as we have for the full-width guides
* reducing the over-all length by 4 cm to avoid interference with the
carriage
Another meeting is scheduled for Tuesday, January 24 at 9:00 am to
discuss progress.
Contract
* Paul has starting on construction documentation.
* Mark has not heard anything from Procurement on the RFP. He will
check on progress.
Prototype Status
* Sasha replaced a trigger PMT and using a new propagation speed
calibration, he gets 98 ps resolution, 90 ps if he restricts
triggers to a narrow region at the center of the counter. The
calibration was obtained by taking data with an americium source at
various positions along the counter.
Construction
* Paul showed us the first light guide with the latest design.
* Ian is working on structure for gluing together three modules at a
time. The system will allow rotation by 180 degrees.
Action Items
* Initiate procurement of the 10-stage tubes.
* Test the 8-stage tubes.
* Check on the status of the Construction Contract.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_January_19,_2012"
References
20.
https://mailman.jlab.org/pipermail/halld-pid/2011-December/000267.html
21.
https://mailman.jlab.org/pipermail/halld-pid/2011-December/thread.html#start
--
Mark M. Ito
Jefferson Lab (www.jlab.org)
(757)269-5295
More information about the Halld-pid
mailing list