[Halld-pid] Time-of-Flight Meeting Minutes, October 25, 2012
Mark M. Ito
marki at jlab.org
Thu Oct 25 16:12:08 EDT 2012
Find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_October_25,_2012#Minutes
_____
GlueX TOF Meeting, October 25, 2012
Minutes
Present:
* FSU: Paul Eugenio, Sasha Ostrovidov
* JLab: Eugene Chudakov, Chuck Hutton, Mark Ito (chair),
Announcement
* The second shipment of 30 PMTs has been sent from Hamamatsu. they
have not yet arrived at FSU. The [27]nominal shipment schedule is
posted on this wiki.
Mechanical Design
Mini-TOF Construction
Paul reviewed [28]his wiki page (standard GlueX username and password)
showing progress and status. Photos of some of the machined parts are
also shown.
TOF Gluing Fixture
Machine shop work for the [29]gluing structure is underway. Parts for a
nine-bar fixture are being made though only a five-bar version will be
constructed initially. Ian Winger will start assembly next week.
TOF Module Wrapper
Paul will put together a wiki page on this item, a long rectangular
channel to help wrap the scintillator. An example was shown as part of
his talk at the last collaboration meeting.
Contract Status
Assessment of PMT batch 1
Sasha has been looking at the 38 PMTs received from Hamamatsu on
October 5. A MySQL database has been set up to store parameters and
test results for each tube. See [30]his wiki page for details.
H showed results from gain measurements done on each tube done by
measuring the position of the single-photo-electron peak. The results
track the data sheet from Hamamatsu to about 5% for a given tube.
The results for quantum efficiency show the first two tubes with vastly
different values (a factor of four difference). The measurement is done
with a Americium source and after correction for gain, give a relative
value for the cathode sensitivity between the two tubes. Sasha is
checking his set-up.
FSU will send four tubes, including the two already tested, to JLab and
the quantum efficiency measurement will be repeated.
Procurements
The two long-lead-time items are the scintillator and the light guide
material.
1. scintillator The PO went out on October 3rd. since then Paul called
Eljen and he expects the first-article counters to arrive on
November 21.
2. light-guide material The order got stuck in FSU Purchasing, but was
finally issued earlier this week. Ninety-two feet of acrylic bar
(in four-foot sections) is expected to arrive November 5. The
machine shop is set up to machine the long light-guides for the
half-width counters. The first patch of acrylic will feed that
process. Then they will set up for the standard light-guides.
Paul is still pursuing getting ESR material in rolls rather than in
small sheets. He is putting together a specification document to
explain the intended use and importance of the larger sheets.
Change request
Mark posted, on the DocDB, [31]documents related to the TOF change
request we submitted at the end of September. The schedule changes were
made to facilitate tracking under the Project's earned-value management
system (EVMS).
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_October_25,_2012"
References
27. https://halldweb1.jlab.org/wiki/index.php/TOF_PMT_Shipping_schedule
28. http://hadron.physics.fsu.edu/wiki/index.php/MiniTOF
29. http://hadron.physics.fsu.edu/wiki/index.php/GluingStructure
30. http://hadron.physics.fsu.edu/wiki/index.php/GlueX_Time-of-Flight
31.
http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=2109
--
Mark M. Ito
Jefferson Lab
marki at jlab.org
(757)269-5295