[Halld-pid] Time-of-Flight Meeting Minutes, September 27, 2012
Mark M. Ito
marki at jlab.org
Fri Sep 28 16:55:01 EDT 2012
Folks,
Find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_September_27,_2012
.
-- Mark
_____
GlueX TOF Meeting, September 27, 2012
Minutes
Present:
* FSU: Paul Eugenio, Sasha Ostrovidov
* JLab: Chuck Hutton, Mark Ito (chair), Elton Smith, Tim Whitlatch,
Beni Zihlmann
Mini-TOF Construction
Paul reports that construction materials are coming in. There was a
delay on a large steel channel, which we are getting from a company
near the Lab. We had to buy a 20 foot piece though only 10 is needed.
TOF Procurements
* Materials are arriving for the gluing jig.
* Specifications for the scintillator were sent to Eljen and Saint
Gobain. Paul has only heard back from Eljen.
* The AJ200 scintillator (new designation) is being produced at Eljen
on revamped machines. We can get scintillator from them sooner than
anticipated, within six weeks of order.
* Additional quotes were requested for UVT acrylic rods. Paul found a
company that can provide the same material as the vendor we have
been using, but with a better delivery schedule. 240 feet can be
delivered in six weeks. Two rods have been purchased from the new
company. They will be evaluated. Elton suggested using a laser and
visually observing the amount of scattering to do a quick
comparative/qualitative evaluation with respect to the material
already in hand.
* Paul is trying again to get ESR daylighting film from 3M in long
rolls rather than small sheets.
TOF Construction
* The gluing jig has been redesigned to allow gluing of nine modules
at a time, with adequate spacing between modules.
* Ian Winger is working on a jig to help with smoothing the wrapping
operation. A U-channel will hold the wrapping and scintillator.
* Paul has been doing tests with RTV for mounting attaching the PMT's
to the light guides. He got two types, RTV 615 and RTV 655, from
Momentum Products (a spin-off of GE silicon). RTV 615 has been used
at other experiments. Initial tests look good; a twenty pound
weight was suspended from the far end of the PMT and the joint
held. The PMT was removed with a razor blade and the surfaced
cleaned up nicely with Kimwipes and silicone solvent.
Contract
Mark and Paul will get together after the meeting by phone to discuss
the Change Request for supporting EVMS accounting now that the contract
is in place.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_September_27,_2012"
--
Mark M. Ito
Jefferson Lab (www.jlab.org)
(757)269-5295
More information about the Halld-pid
mailing list