[Halld-pid] Start Counter Meeting Minutes, April 18, 2013
Mark M. Ito
marki at jlab.org
Thu Apr 18 13:44:51 EDT 2013
Find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_April_18,_2013#Minutes
.
_____
GlueX Start Counter Meeting, April 18, 2013
Minutes
Present:
* FIU: Eric Pooser
* JLab: Eugene Chudakov, Chuck Hutton, Mark Ito (chair)
Construction
Five counters have been bent and Eljen and shipped to McNeal where they
have been received. McNeal is waiting for a PO before starting
machining the counters. Eric is monitoring the situation.
The test stand has undergone a substantial redesign after Eric
discussed the design with Carlos Ortega of the FIU Physics machine
shop. Final drawings will be done today. Hopefully machining can start
next week.
FIU has received their new CAEN HV cards. They have not been tested
yet.
Chuck checked with Jim Fochtman about the mechanical interface between
the target and the start counter. Nothing has changed on that front.
Some time ago Chuck and Eric discussed the idea of matching the inner
radius of the support ring and the inner support foam. This would
simplify mounting the counter on the construction frame. They will
discuss this further offline.
Contract
Mark has reviewed the technical proposal and it appears acceptable.
Bruce Lenzer did have some QA issues with it, but it was thought that
these could be addressed at the time of the readiness review. The terms
and conditions for the proposal from FIU will be sent tomorrow.
Schedule
Mark showed the [20]latest schedule from the recent rebaselining
effort. It shows final drawings done by June 14, not so far away!
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_April_18,_2013"
References
20. https://halldweb1.jlab.org/talks/2013-2Q/start_counter.html
--
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295