[Halld-pid] Time-of-Flight meeting minutes, December 5, 2013
Mark Ito
marki at jlab.org
Sun Dec 8 14:34:49 EST 2013
ID checkers,
Find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_December_5,_2013#Minutes
.
-- Mark
_______________________________________________________________
GlueX TOF Meeting, December 5, 2013
Minutes
Present:
* FSU: Paul Eugenio, Sasha Ostrovidov
* JLab: Eugene Chudakov, Chuck Hutton, Mark Ito (chair), Tim
Whitlatch, Beni Zihlmann
Announcements
We congratulated the FSU team for completing delivery of all TOF
modules to JLab. Well done!
Material procurement for support frame
* Most of the pieces are in for the bench shield[?].
* C-channels are due in next week. [Added in press: these are
supposed to come in December 16.]
* FSU has enough silicon foam rubber for the support frame. They will
bring it up on the next trip.
* Tim will call a meeting to make sure we have accounted for all of
the parts and assign responsibility for providing them.
Module installation plan
* Hussein will be coming to JLab to help with assembly.
* Paul would like to come up and help start installation before the
holiday break [this was before we heard about the C-channel
delivery schedule.]
* Chuck is working on an updated [21]installation document.
* Tim suggested that we go though the current version of the document
as a way to review the complete parts inventory. We did this,
step-by-step, and we addressed most, if not all, of the parts
issues.
End of Construction Contract
* FSU has an official end-of-contract in January. This may have to be
extended.
Retrieved from
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_December_5,_2013
References
21. https://halldweb1.jlab.org/talks/2013-4Q/D00000assy.pdf
--
Mark M. Ito, Jefferson Lab, (757)269-5295
More information about the Halld-pid
mailing list