GlueX TOF Meeting, May 9, 2013
Minutes
Present:
* FSU: Paul Eugenio, Sasha Ostrovidov
* JLab: Mark Ito (chair), Beni Zihlmann
Announcement
There will be a TOF assembly and installation meeting, Friday, May 10,
at 10 am in ARC 428. FSU will participate via video-conference.
Collaboration Meeting Schedule
We looked over the schedule for Session IIIb. Paul will give the TOF
report at the meeting. Chuck offered to prepare representative drawings
for Paul's presentation. The offer accepted.
Review of last TOF bi-weekly meeting
We reviewed the [31]minutes from the April 25 meeting.
HV Board Loan from Hall B
Mark spoke to Sergey Boyarinov and was told that Hall B has lots of
spare 1450 series HV boards. They will not be using them for CLAS12.
Paul indicated that FSU could use two. Mark will arrange shipment to
FSU.
Invoice Backup Info
Mark spoke to Kathleen Jones and she has contacted Emily Nerona of FSU.
FSU will start work this week on providing the more detailed
information we agreed on at the Readiness Review for the current and
past invoices.
Construction Updates
* The replacement for the counter with a poor attenuation length
arrived.
* After the last meeting there was an exchange on the email list. FSU
proposed that PMTs should be matched with scintillators as well as
to each other. This requires all of the scintillator to be measured
before gluing to PMTs.
* Scintillator testings has continued. Seventy eight are done, 14
left to go. They should all be done in day or two.
* All of the scintillators measured since the last meeting have
acceptable attenuation length.
* Visual inspection of the bars revealed on counter with a few small
bubbles and some with minor dings and scratches, probably received
during packing at Eljen. These imperfections have been noted but
are not expected to affect performance.
* In addition to the counters that Eljen warned us about, those short
by 1/8 inch, some of the counters were measured at about 1/16 inch
short. Again this should not effect the mechanics of mounting the
counters. Each module has a center mark. If all marks are aligned
in the frame then these differences should be split between the two
ends.
* Ian and Randall made new tool to make the creasing of the ESR
easier. It is a roller that presses the material into the corner of
a long channel.
* Three bars were mistakenly wrapped with the protective transparent
film still on the scintillator. Surgery was done to remove the film
and the procedures will be changed to make sure that it does not
happen again.
* There is a new plan to use the gluing stand to do nine counters at
a time rather than five. This is consistent with the capacity of
the original design. Eight standard counters and one half-width
counter can be accommodated at once. The next batch should be
started today.
* Students are coming back from their post-semester break and
full-time shifts should start Monday. This week there were some
students helping with light guide attenuation tests.
Invoicing Changes and Status
Mark created a [32]wiki page to track invoices from FSU to JLab (wiki
account required to view).
Installation Plan and Document
Paul reviewed the [33]shipping plan (standard GlueX username and
password required) they are developing at FSU. In particular he showed
a design of the shipping container. Four modules are packed into a
container.
Channel Labeling Scheme
David Lawrence is working on the software channel labeling scheme based
on Fernando's channel assignments. We need to get the scheme for the
TOF and give him comments.
Simulation Geometry Status
The Monte Carlo still does not have the split counters (half-width) in
the default configuration. Beni will look into what it takes to put
them in.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_May_9,_2013"
References
31.
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_April_25,_2013#Minutes
32.
https://halldweb1.jlab.org/wiki/index.php/Private:FSU_Construction_Invoices
33.
http://hadron.physics.fsu.edu/wiki/index.php/Module_Storage_and_Shipping_Plan#Shipping_Plan
--