[Halld-pid] Start Counter Meeting Minutes, October 17, 2013
Mark M. Ito
marki at jlab.org
Fri Oct 18 09:27:47 EDT 2013
Folks,
Find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_October_17,_2013#Minutes
.
-- Mark
_________________________________
GlueX Start Counter Meeting, October 17, 2013
Minutes
Present:
* FIU: Werner Boeglin, Eric Pooser
* JLab: Eugene Chudakov, Jarrod Fitzpatrick, Mark Ito (chair), Tim
Whitlatch, Beni Zihlmann
Construction News
* Tim told us that the aluminum mandrill for construction of the
foam/carbon-fiber support has been made.
* We discussed the geometry of the support structure. FIU needs to
finalize design of the construction fixture and there were some
questions about the dimensions of the inner foam, carbon fiber
reinforcement, and the aluminum support ring (all components used
in the actual detector support). Tim will look into getting the
latest set of drawings to FIU so that we can continue the
discussion.
* The POs to Eljen and McNeal for the scintillator and machining
respectively ran into a snag in the FIU procurement process. They
should go out next week.
* The test stand is 99% complete. There are a few parts left to put
together.
* Eric has been browsing the McMaster catalog for parts for the
assembly jig.
* Werner has been thinking about the exact materials for bands
holding the counters on the inner foam as well as the related part
of the construction procedure; he wants to minimize forces on the
scintillator.
Electronics
* Eric report that Fernando will send down all of the cables FIU will
need to test read-out.
* We discussed to utility of doing a complete test of the detector
with the final electronics chain for all channels. Although that
has been the nominal plan, it may not be the most efficient use of
manpower. Beni and Mark will discuss what would be needed and
report the the group.
Installation
We decided to maintain April 2014 as a target date for installation of
the start counter.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_October_17,_2013"
--
Mark M. Ito, Jefferson Lab, (757)269-5295, marki at jlab.org
More information about the Halld-pid
mailing list