[Halld-pid] Start Counter Meeting Minutes, October 17, 2013
Fernando J Barbosa
barbosa at jlab.org
Fri Oct 18 09:45:23 EDT 2013
Hi Mark,
You need to tell me in advance what you will need at FIU. For example, I
indeed have all the cables but they are scheduled to be installed in the
hall. So, to avoid any further misunderstandings:
1) what needs to be shipped to FIU
2) when
Best regards,
Fernando
On 10/18/2013 9:27 AM, Mark M. Ito wrote:
> Folks,
>
> Find the minutes below and at
>
> https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_October_17,_2013#Minutes
> .
>
> -- Mark
> _________________________________
>
> GlueX Start Counter Meeting, October 17, 2013
> Minutes
>
> Present:
> * FIU: Werner Boeglin, Eric Pooser
> * JLab: Eugene Chudakov, Jarrod Fitzpatrick, Mark Ito (chair), Tim
> Whitlatch, Beni Zihlmann
>
> Construction News
>
> * Tim told us that the aluminum mandrill for construction of the
> foam/carbon-fiber support has been made.
> * We discussed the geometry of the support structure. FIU needs to
> finalize design of the construction fixture and there were some
> questions about the dimensions of the inner foam, carbon fiber
> reinforcement, and the aluminum support ring (all components used
> in the actual detector support). Tim will look into getting the
> latest set of drawings to FIU so that we can continue the
> discussion.
> * The POs to Eljen and McNeal for the scintillator and machining
> respectively ran into a snag in the FIU procurement process. They
> should go out next week.
> * The test stand is 99% complete. There are a few parts left to put
> together.
> * Eric has been browsing the McMaster catalog for parts for the
> assembly jig.
> * Werner has been thinking about the exact materials for bands
> holding the counters on the inner foam as well as the related part
> of the construction procedure; he wants to minimize forces on the
> scintillator.
>
> Electronics
>
> * Eric report that Fernando will send down all of the cables FIU will
> need to test read-out.
> * We discussed to utility of doing a complete test of the detector
> with the final electronics chain for all channels. Although that
> has been the nominal plan, it may not be the most efficient use of
> manpower. Beni and Mark will discuss what would be needed and
> report the the group.
>
> Installation
>
> We decided to maintain April 2014 as a target date for installation of
> the start counter.
>
> Retrieved from
> "https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_October_17,_2013"
>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: barbosa.vcf
Type: text/x-vcard
Size: 265 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/halld-pid/attachments/20131018/750c9100/attachment-0002.vcf>