[Halld-pid] Start Counter Meeting Minutes, April 3, 2014
Mark Ito
marki at jlab.org
Sat Apr 5 13:08:47 EDT 2014
Folks,
Find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_April_3,_2014#Minutes
.
-- Mark
_____________________________________________________________________
GlueX Start Counter Meeting, April 3, 2014
Minutes
Present:
* FIU: Werner Boeglin, Eric Pooser
* JLab: Eugene Chudakov, Mark Ito (chair), Chuck Hutton, Tim
Whitlatch
Detector Construction Status
Eric gave us the update.
Eljen has made fifty bent scintillator bars. They arrived at McNeal
yesterday. The team at McNeal is meeting to detail plans for machining.
They will start in a week and the process should take about a week or
two. The hope is to receive the counters at FIU at the end of April.
Testing rate is 5 per day.
The mis-alignment study continues. There is an undergraduate working on
it.
Fabrication of the assembly jig will start next week. That should take
a week or two.
Final construction should start in the middle of May.
Support structure construction status
The Rohacell block are being glued now. Tom Carstens is doing that.
We looked at the final drawings for the support structure. They are now
all out for signatures.
Werner reminded us that we plan to delay drilling holes in the second
aluminum collar, in case some problem is identified with the hole
locations in the first one.
Readiness Review
Mid-May looks to be a likely time for a Readiness Review. We also need
to review plans for having Nick Sandoval travel to FIU to set-up the
electronics.
BlueJeans
We used BlueJeans for this meeting without major incident, which is
good.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_April_3,_2014"
--
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295