[Halld-pid] Time-of-Flight Meeting Minutes, January 16, 2014
Mark Ito
marki at jlab.org
Tue Jan 21 15:37:12 EST 2014
People,
Find the minutes below and at:
https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_January_16,_2014#Minutes
-- Mark
____________________________________
GlueX TOF Meeting, January 16, 2014
Minutes
Present:
* FSU: Paul Eugenio, Sasha Ostrovidov
* JLab: Chuck Hutton, Mark Ito (chair), Beni Zihlmann
Installation
Paul was at the Lab earlier in the week with Hussein (who is still in
Newport News). A lot of progress was made in preparations for
installation. There are a lot of adjustments/height-settings that have
to be done and the details of the procedure are being worked out. Tom
has been consulting on details as well. A few modules were laid out on
the frame to test the fit of the various components.
The number of the threaded standoffs made turned out to be much fewer
than required. FSU is making the balance now and they should be ready
by next week when Paul goes back to the Lab on Tuesday. Turns out there
are already enough of the corresponding nuts on hand due to an extra
order that came from McMaster.
Electronics
Paul will return the CAEN TDC module borrowed from JLab to Fernando.
The FSU module was sent back to CAEN for repair and has now been
returned.
Testing Results
Sasha has been working on test results from the short paddles. He has
got things down to about 150 ps, including application of time-walk
corrections. The standard modules gave 90 ps, but they are two-ended,
unlike the short paddles.
Contract
A contract extensions has been approved. Paul will look into getting a
signature on it at the FSU end.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_January_16,_2014"
More information about the Halld-pid
mailing list