[Halld-pid] Start Counter Meeting Minutes, March 20, 2014
Mark Ito
marki at jlab.org
Fri Mar 21 22:24:43 EDT 2014
Folks,
Please find the minutes below and at
https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_March_20,_2014#Minutes
.
-- Mark
____________________________________________________________________________________
GlueX Start Counter Meeting, March 20, 2014
Minutes
Present:
* FIU: Werner Boeglin, Eric Pooser
* JLab: Chuck Hutton, Mark Ito (chair)
Find a recording this meeting [23]here.
Announcements
Werner initiated a no-cost extension to the contract. It would have
expired at the end of the month. The extension has been fully executed
(both parties have signed).
Review Minutes from Previous Meeting
We looked over [24]items from the March 6th meeting.
* "y"-scan with the Test Stand: the time resolution was measured for
different positions of the SiPMs with respect to the scintillator
along the "radial" direction. The qualitatively, the results show
less dependence on position than we might have feared; an offset of
up to 0.5 mm is not serious. The measurements do need to be
repeated; the translation stage was damaged and that has been
holding things up.
* Eric has been working on the calibration procedure. He has a
prototype set of classes for doing the calibration. He is drafting
a proposal for the set of calibration constants we will need. The
parametrization for the time-walk correction is still being
studied. He will give a talk on his work at the Calibration Meeting
next week.
Review of Bruce's Q/A Visit to Eljen
We discussed Bruce Lenzer's visit and the [25]notes from Mark on the
conference call we had with folks at Eljen. Things look a lot better
now. We thought that it really helped that Bruce was able to go out
there. Thirty good scintillators have already been produced, twenty
more (to complete the order) should be done in two weeks.
Eric will follow up with McNeal on taking shipment of these first
thirty ASAP. Even if they prefer to have all fifty on hand before
starting production, we would like to know if they like what they see
with this batch.
Support Structure Construction Status
Eric gave us a [26]very detailed report on measurements of the
dimensions of one of the paddles, complete with pictures. The counter
was wrapped in aluminum foil as we plan to do. This counter with
wrapping turns out to be the same thickness as the nominal scintillator
itself, without wrapping, thus this paddle is under spec.
Eric will go ahead and measure a few more of the paddles on hand at
FIU.
We decided if these additional measurements indicate that the width
being under spec is typical, we will fix on a gap between the
scintillators of 100 microns when sizing dimensions of the the support
structure.
Werner floated the idea of making two aluminum support rings and only
drilling holes in one, keeping the other in stock in case there are
surprises.
Eric suggested we try to get measurements from McNeal as well. We
agreed that this should be pursued.
Retrieved from
"https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_March_20,_2014"
References
23.
https://halldweb1.jlab.org/talks/2014-1Q/start_counter_2014-03-20/index.htm
24.
https://halldweb1.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_March_6,_2014#Minutes
25.
https://halldweb1.jlab.org/wiki/index.php/Private:Quality_Assurance_Meeting_with_Eljen,_March_17,_2014
26. https://halldweb1.jlab.org/talks/2014-1Q/Paddle_Measurements.pdf
--
Mark M. Ito, Jefferson Lab, marki at jlab.org, (757)269-5295