GlueX Start Counter Meeting, April 21, 2016, Minutes
Present:
* *FIU*: Werner Boeglin
* *JLab*: Mark Ito (chair), Simon Taylor
* *NU*: Sean Dobbs
Calibration Update
Propagation Delay Parametrization
Sean Propagation Time Corrections identified an inconsistency
<https://halldweb.jlab.org/talks/2016/start_counter_prop_time_corr.pdf>
in how the propagation time delay was parametrized between data and
Monte Carlo. The issue was fixed in Pull Request #338
<https://github.com/JeffersonLab/sim-recon/pull/338>. From the pull
request:
* Make propagation time corrections be consistently defined in terms
of path length through scintillator
* Rewrite plugins to pull expensive calculations outside of locks
* Other minor changes
Charged-Track/Start-Counter Matching
Sean did a study showing the distribution of azimuthal angle within a
single start counter sector versus z where the azimuthal angle is
determined by the intersection of the track with the start counter and
only track/start-counter matches are considered. Plots were made for
each of the 30 sectors
<https://halldweb.jlab.org/wiki/images/a/a1/Sc_match.pdf>.
There is feature in the nose sections where a bias is seen in some
counters toward higher or lower azimuth, depending on the counter. The
bias direction and amplitude seems to be a smooth function of sector
number making geometry a likely candidate for the source of the effect.
Without correction we may have to increase the tolerance for a match in
the nose region.
Pre-Amp Strain Relief
Although this work was done at the beginning of the run, the photos
showing the strain relief system were never shown at this meeting. See
the photos and accompanying email from the designer
<https://halldweb.jlab.org/talks/2016/start_counter_strain_relief/> for
details.
mcsmear Parameters
We reviewed the parameters
<https://halldweb.jlab.org/wiki/index.php/Mcsmear_updates#START_COUNTER>
again. See the discussion from last time
<https://halldweb.jlab.org/wiki/index.php/GlueX_Start_Counter_Meeting,_March_24,_2016#mcsmear_parameters>.
In discussing the energy resolution, we noted that we not have a good
measurement of the number of photons per MeV and the measured resolution
in real data contains both the intrinsic energy loss fluctuations as
well as the effect of photon statistics. In Monte Carlo, these effects
are put in separately, and so must be disentangled in the data if data
is to be a guide.
NIM/TDR
Werner reported that Eric Pooser has started a TDR contribution for the
start counter.
Retrieved from
"https://halldweb.jlab.org/wiki/index.php?title=GlueX_Start_Counter_Meeting,_April_21,_2016&oldid=74638"
* This page was last modified on 21 April 2016, at 14:09.
--
marki at jlab.org, (757)269-5295
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-pid/attachments/20160421/40662de8/attachment.html>
More information about the Halld-pid
mailing list