[Halld-pid] Start Counter Meeting Minutes, June 2, 2016
Mark Ito
marki at jlab.org
Fri Jun 3 15:25:57 EDT 2016
Folks,
Please find the minutes below and at https://goo.gl/dYg4gJ .
-- Mark
__________________
GlueX Start Counter Meeting, June 2, 2016, Minutes
Present:
* *FIU*: Werner Boeglin, Mahmoud Kamel
* *JLab*: Mark Ito (chair), Eric Pooser, Simon Taylor, Beni Zihlmann
Geometry
Simon is close to submitting a pull request with new geometric
parameters for the start counter. He is currently dealing with an
overlap issue with the CDC. He is using the recently done survey as a
guide for the changes. It shows a tilt larger than we thought we had,
0.3 degrees down. (For comparison we had 0.6 degrees in Fall 2014.) On
the upstream end the start counter is 3.4 mm above nominal.
Simon is also working on widening the cut for matching charged tracks to
the start counter in the nose region. Previous studies have shown the
phi distribution of tracks at the intersection with the start counter
not centered on the nominal counter center. The shift is not always in
the same direction.
Calibration
After working with Sean to correct the propagation time calibration
implementation, Mahmoud measured time resolution for three
representative runs.
Run Sigma (ps)
11366 286
11405 284
11455 293
He tried running with run-by-run calibrations and did not see an
improvement over the single set of constants already present in the CCDB
(improvement of 3 ps). We will go ahead and use the single set.
Efficiency
Mahmoud showed start counter hit efficiency using crossing charged
tracks. If he requires more than 20 hits on the charged track, the
efficiency goes up to 99%. Unfortunately, there are not enough tracks in
the forward part of the nose that satisfy this criteria to get a
meaningful efficiency measurement there.
NIM/TDR
Eric is back in action in Newport News and will be working on the NIM
paper.
Swiss Efficiency
Beni noted that the Gotthard Base Tunnel was recently completed on time
and under budget, apropos of nearly nothing.
Retrieved from
"https://halldweb.jlab.org/wiki/index.php?title=GlueX_Start_Counter_Meeting,_June_2,_2016&oldid=75440"
* This page was last modified on 3 June 2016, at 15:24.
--
marki at jlab.org, (757)269-5295
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-pid/attachments/20160603/979b9865/attachment.html>
More information about the Halld-pid
mailing list