[Halld-pid] Time-of-Flight Meeting Minutes, May 22, 2019

Mark Ito marki at jlab.org
Thu May 23 12:05:39 EDT 2019


Colleagues,

Please find the minutes here 
<https://halldweb.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_May_22,_2019#Minutes> 
and below.

   -- Mark

_______________________________________________________


    Minutes, GlueX TOF Meeting, May 22, 2019

Present:

  * *FIU: * Edmundo Barriga
  * *FSU: * Jason Barlow, Paul Eugenio, Sasha Ostrovidov
  * *JLab: * Thomas Britton, Tolga Erbora, Ashley Ernst, Mark Ito
    (chair), Simon Taylor, Tim Whitlatch

There is a recording of this meeting <https://bluejeans.com/s/eXbdh/> on 
the BlueJeans site. Use your JLab credentials to access it.


      Review of minutes from the last meeting

We went over the minutes from the meeting on May 8 
<https://halldweb.jlab.org/wiki/index.php/GlueX_TOF_Meeting,_May_8,_2019#Minutes>. 
Ashley had a look at the geometry. The changes needed for the upgrade 
should not be too bad.


      Upgrade Status


        Procurement

Mark reported:

  * The PR for 17 additional phototubes has gone into Procurement. We
    should inventory the spares already in hand at JLab.
  * Polishing supplies that Paul requested were ordered from MSC. They
    should arrive at FSU tomorrow.


        Engineering Work

Tim reported:

  * Everything in the Hall is ready to go.
  * Nothing will be done until the DIRC installation is complete,
    probably several more weeks.
  * JLab has the drawings in hand for the brackets and will send them
    out to be made.
  * Collars will made at FSU.
  * Paul reports that they have reviewed the drawings Stephanie
    Worthington sent and they look good.
  * Paul expressed some misgivings at the design of the racks to store
    the modules when they arrive at JLab. He and Tim will discuss this
    further.
  * The gluing fixture will be mounted in the Hall as it was during the
    initial installation.


        Construction

Paul reported:

  * The scintillator bars have arrived at FSU. The boxes will get opened
    tomorrow. Inspection routine will be performed.
  * Paul will be sending in an order for more RTV and primer.
  * The current batch of light guides are ready to have their ends
    trimmed off.
  * The ESR forming device is getting made.
  * Paul has been thinking about the beam support box needed for air
    light guides across the beam hole.
  * Ashley asked if we would need lucite shielding in the new
    configuration. The DIRC will provide some level of shielding but not
    over all of the TOF near the beamline. This will require further
    thought.


        Software

Paul pointed out that there are many software tasks that need to get 
done to support the new configuration beyond the geometry specification.

  * HV and scaler guis
  * Monitoring histograms
  * HDvis and hdview2
  * TOF reconstruction
  * TOF calibration

Retrieved from 
"https://halldweb.jlab.org/wiki/index.php?title=GlueX_TOF_Meeting,_May_22,_2019&oldid=92747"

  * This page was last modified on 23 May 2019, at 12:02.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld-pid/attachments/20190523/a57ada22/attachment.html>


More information about the Halld-pid mailing list