Hello Richard,

I think that the proposals/(test plans) look good enough,
we could discuss details and answer questions (if any)
later. I would  submit it asap., time is very short.

I will update you with the test preparation status shortly.

Cheers,
        Alex


On Tue, 19 Oct 2010, Richard Jones wrote:

>  Alex,
>
> Here is the second part of our parasitic beam time request.  Please read and 
> give immediate feedback, as I want to get this sent in to the Hall B 
> management by the end of the day today, if possible.
>
> http://zeus.phys.uconn.edu/~senderovich/GlueX/Tagger/Reports/MicroscopeBeamTest_plan-2-2010/MicroscopeBeamTest_plan-2-2010.pdf
>
> -Richard J.
>
>
>