Hi Richard,
This seems to be a question for controls . The original plan was to have
just fibers going to the counting house, no coax cables (maybe just a
few now).
Best regards,
Fernando
On 11/6/2012 11:51 AM, Richard Jones wrote:
> Hi Fernando,
>
> The cabling plans that I have seen have focused on detector
> subsystems. I don't think we have established plans yet for beamline
> related sensors that are not a part of the data acquisition. Examples
> of this would be coax cables for video cameras looking at the radiator
> target, and background rate monitor scintillators that we will want
> placed at various locations along the beamline. How many of these and
> where they will be placed is not fixed yet, but it will be very useful
> to have patch panels with connections to the counting house so we can
> look at various things when beam is in the hall. The same thing goes
> for the collimator cave. Especially during commissioning it will be
> useful to have measurements of background in the cave, and know how
> things are changing with beam tune, etc.
>
> When I was thinking about these things, it struck me that it would be
> useful to also be able to view the currents from the active collimator
> directly in the counting house, and do the signal digitization there.
> This way we do not have to put a data acquisition crate in the
> high-radiation area of the collimator cave and risk it rebooting,
> etc. Especially during commissioning this would seem to be useful.
>
> -Richard J.
>
> On 11/6/2012 10:14 AM, Fernando J Barbosa wrote:
>> Hi Richard,
>>
>> I have been talking about cables and such for years and you never
>> requested these. Are these anywhere on the plans? Any details?
>>
>> Best regards,
>> Fernando
>>
>> On 11/6/2012 9:08 AM, Richard Jones wrote:
>>> Hi Fernando,
>>>
>>> I don't know where this request should be routed, so I am sending it
>>> directly to you. I would like to make sure that we have coaxial
>>> connections from the upstream wall of the collimator cave to the
>>> counting house. Here are some signals that we would like to be able
>>> to read directly, and minimize how much DAq electronics we need to
>>> place in a hot radiation area.
>>>
>>> 1. output signals from the active collimator: 8
>>> 2. cave background rate monitor scintillators: 2-4
>>>
>>> A panel of 16 or 24 would be sufficient, I believe. There are also
>>> controls for the collimator translation stage and associated limit
>>> switches. Further downstream there is the converter target ladder,
>>> which may be inside the cave or outside, depending on the ability to
>>> shield the stray magnetic field from the pair spectrometer. I just
>>> want to make sure we have cables and cable trays for these
>>> interconnects, as it may be difficult to add them later.
>>>
>>> -Richard Jones
>>>
>>
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/halld-tagger/attachments/20121106/6467232b/attachment.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: barbosa.vcf
Type: text/x-vcard
Size: 265 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/halld-tagger/attachments/20121106/6467232b/attachment.vcf
More information about the Halld-tagger
mailing list