<div dir="ltr">Fernando,<div><br></div><div>I am going to propose that we set things up in the ESB area when we arrive, and do what setup and testing we can there prior to the move-in date in the first week of October or thereabouts. Any objections?</div>
<div><br></div><div>-Richard Jones</div></div><div class="gmail_extra"><br><br><div class="gmail_quote">On Thu, Aug 21, 2014 at 10:03 AM, Fernando J Barbosa <span dir="ltr"><<a href="mailto:barbosa@jlab.org" target="_blank">barbosa@jlab.org</a>></span> wrote:<br>
<blockquote class="gmail_quote" style="margin:0 0 0 .8ex;border-left:1px #ccc solid;padding-left:1ex">Hi Richard, Alex,<br>
<br>
We will start removing the electronics from the tagger hall on 22 Sept 2014 in preparation for beam on 29 Sept 2014. All the cables will be disconnected from the modules but remain in place with the mini-racks; we then remove the crates/chassis with the modules and move them to a safe place, probably the ESB.<br>
<br>
You have indicated that you will be bringing the TAGM to JLab during the week of 9/1. In view of this, you only have two weeks (weeks of 9/8 and 9/15) to install, connect and test the TAGM. Is this enough time to do any significant work (setup software, controls, readout, etc)? Or should we plan to work in the ESB, which allows limited testing (limited number of cables, no 208V for the crates so power is an issue anywhere outside of the tagger hall)?<br>
<br>
Please work out a viable plan and let me know ASAP. If we are not going to do anything in the tagger hall, we could go ahead and start removing the electronics earlier so we are not rushing later.<br>
<br>
Best regards,<br>
Fernando<br>
</blockquote></div><br></div>