Due to the weather conditions the lab will close at 1pm and we have to
cancel our meeting today. Still, there are some links/pictures in the
agenda you may want to look at. During the last few weeks there was
significant progress in many directions:
- Clean room construction goes fast (see linked pictures)
- All the PCBs are back from the company after cleaning. Last information
from Chris: they look good and hold the nominal HV.
- First article cathode foils (4X3 panels) arrived and we started the
inspection in the Hall B clean room. We have remarks concerning the
packing, but other than that there were no problems found on one of the
panel that was inspected. Allflex expects yield of 80-85% (see the attached
report showing also what some of the problems they had during the
production).
- Wire stringing: most of the parts are mounted, waiting for the
strongback. We got the stepper motor controller.
- Tension measurements were demonstrated (see attached pictures) to work
using permanent magnet and ~10mA AC from a generator put on the
individual wires. Same laser sensor (as for the position measurements) was
used to measure the amplitude of the oscillations and find the resonance.
- Using methane in the chamber resulted in significant reduction of the
after-pulses and very high gains were achieved.
I don't think it will be practical to have a meeting next week, so happy