Dear trackies,
The CDC has now been tested with all the electronics, on-detector HV
distribution cabling and LV cabling and in its final configuration. I
placed GlueX-doc-2377 on the portal (also attached for those w/o access)
which summarizes our pre-installation tests. Very nice!
Special thanks to Nick Sandoval and Michael Klopf for the installation
of the electronics, cabling, tests and all the fine touches that
complete the CDC. The CDC is now ready for installation in the hall but
Beni will first perform additional tests with the fADC125s.
Happy Holidays,
Fernando
-------------- next part --------------
A non-text attachment was scrubbed...
Name: CDC Pre-Installation Tests.pdf
Type: application/pdf
Size: 460349 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/halld-tracking-hw/attachments/20131217/fa65ef51/attachment-0001.pdf
-------------- next part --------------
A non-text attachment was scrubbed...
Name: barbosa.vcf
Type: text/x-vcard
Size: 265 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/halld-tracking-hw/attachments/20131217/fa65ef51/attachment-0001.vcf
More information about the Halld-tracking-hw
mailing list