<html><head></head><body style="word-wrap: break-word; -webkit-nbsp-mode: space; -webkit-line-break: after-white-space; "><div>These are online at</div><div><br></div><a href="https://halldweb1.jlab.org/wiki/index.php/February_13,_2013_Tracking_CDC/FDC">https://halldweb1.jlab.org/wiki/index.php/February_13,_2013_Tracking_CDC/FDC</a><div><br></div><div>Apologies for the late email - minutes were up soon after the meeting.</div><div><br></div><div>Naomi.<br><div><br></div><div><p>Present: Curtis, Naomi, Beni, Simon, Lubomir, Eugene 
</p>
<ol><li> Collaboration meeting
<ol><li> 3 talks have been reserved for tracking 
</li></ol>
</li><li> FDC Update
<ol><li> Last production package (#2) completely tested. We started the 
installation of the grounding, will be followed by the cooling system 
and HV cable installation.
</li><li> Beni: third package being tested (#1), all the channels (~3k) working OK except one strip, but could be the electronics.
</li><li> The three installation carts have been surveyed (including one
 for CDC). To check for possible deformations, will load one card with 
155kg (FDC+cables) using the FDC mock-up.
</li></ol>
</li><li> CDC Update
<ol><li>The downstream plenum was installed on Friday, which was CDC tech Kate's last day.  This completes the CDC construction.
</li><li>Amy and Gary have been checking the CDC for leaks, found 
nothing at the downstream plenum and some very small leaks on the inner 
ring of hookup wires where they are soldered onto the transition boards.
  The leaks are difficult to pinpoint so we propose to seal the ends of 
the wires with the same epoxy which was used for this previously; maybe 
the seals became cracked when the wires were positioned for soldering. 
</li></ol>
</li><li>CDC HV Connectors and assembly
<ol><li>The one engineering task remaining is to install the cooling 
ring for the electronics, which must also provide a mount for each of 
the 6 HV connector blocks.  The blocks are on order and will be 
installed at JLab.  Each mount will need to provide strain relief for 
one big HV cable, but not to support all of its weight, just to make 
sure that there are no tight bends where it approaches the CDC.  
Presumably the cables will be supported by some structure attached the 
magnet.  The cooling ring is a polyflo pipe mounted on 12" long Al rods 
which fit into threaded holes in the endplate. Holes have been drilled 
in the pipe so that air can be blown over the electronics.  Details of 
the mount will be discussed at the collaboration meeting.  Clean air 
will be required for the cooling ring.
</li></ol>
</li><li>CDC Testing
<ol><li>CMU needs to send JLab a request for a no-cost extension.  The 
intention is to use the CDC for calibration/testing as much as possible 
before and after installation, to keep it at CMU for testing until 
shortly before its installation date, when it will be transported to 
JLab.  At present the baseline schedule shows the FDC installation into 
the magnet happening in mid-October, so it would seem pragmatic to 
request the extension until late 2013.
<ol><li>CMU's plan for testing the CDC includes taking data with cosmics
 first to verify that each straw can provide a signal and then to 
provide drift-time and amplitude measurements for each straw.  
</li><li>Allowing one day of cosmics per measurement but reading 72 
straws (1 fADC) at a time, 5 days per week, the measurements should take
 10 weeks, excluding time for setup.  
</li><li>Beni has sent cables to CMU for LV, HV and data, enough for 3 
fADCs. With 3 fADCs one set of measurements should take only 4 weeks and
 so we should have time to make measurements at the midpoint and at both
 ends of the chamber.  
</li><li>With 3 fADCs we should also be able to find tracks through at least half of the chamber.
</li><li>During this time we will also be working on the fADC readout, and developing calibration methods and software.  
</li></ol>
</li><li>Manpower will be needed at JLab during CDC installation but we should be able to do the data analysis remotely.
</li><li>We are hoping to be able to use BCAL for triggering during 
post-installation calibration runs with cosmics.  There is a possibility
 that we might get some beam into Hall D in April 2014 when it should be
 in the tagger hall, we should plan for beam tests then or wait until 
October 2014.  Until then the solenoid magnetic field will mostly be 
off, the solenoid will be cooled with N2 but not He.