<html><head></head><body style="word-wrap: break-word; -webkit-nbsp-mode: space; -webkit-line-break: after-white-space; ">Minutes are online at&nbsp;<a href="https://halldweb1.jlab.org/wiki/index.php/March_13,_2013_Tracking_CDC/FDC">https://halldweb1.jlab.org/wiki/index.php/March_13,_2013_Tracking_CDC/FDC</a><div><br></div><div><br></div><div><p>Present: Curtis, Naomi, Mark, Beni, Lubomir, Simon 
</p>
<ol><li> FDC Update
<ol><li> Package #2 moved to JLab for testing on Friday. Beni already started taking data: first cell has no problems.
</li><li> Package #1 moved to Blue Crab after testing showed some gas 
leakage; turned out to be a tube connector on the spacer ring and was 
fixed.
</li><li> Package #3 that had problems with one HV sector on the bottom 
cell, was opened from the bottom side. A small hair/lint was fond on a 
wire in this sector. The package was closed and will be tested soon.
</li></ol>
</li><li> CDC Update
<ol><li>The gas mixer MFCs were exchanged for larger capacity models and
 the CDC now has 50/50 Ar/CO2 flowing through at 1100sccm (one chamber 
volume per day) and exhausting through 6 bubblers into a fume hood.
</li><li>Gary added another rubber support at each corner of the support rail.
</li><li>We are preparing to move the DAQ electronics in.
</li><li>We still need diagrams for the HV mounting blocks and some idea
 of the weight they would have to support. Lubomir and Beni will send 
these. 
</li></ol>
</li><li> Installation Details
<ol><li>Lubomir presented the latest installation schedule for the FDC. 
 Some spikes in manpower (where not enough people were available or only
 a few people can be on the platform working on a task) had been spread 
out, resulting in the installation finishing  several months later than 
previously thought (from November to January).  This gives considerably 
shortened time for CDC installation and commissioning; the no cost 
extension for the CDC work will need further extension.
</li><li>We tried to identify tasks which might benefit from extra 
personnel. CMU's first-year grad students would be available in 
June/July.  For each of the following, would extra people help to 
complete the task earlier...
<ol><li>BCAL installation
</li><li>labelling and bundling the FDC cables
</li><li>testing the HV and LV units
</li><li>cable tray installation?
</li></ol>
</li><li>When would the HV and LV crates be available?
</li><li>When would sufficient fadc125 be available for testing with the FDC? June?
</li></ol>