[Halld] Spring Run Update

David Lawrence davidl at jlab.org
Wed Apr 1 15:20:13 EDT 2015


Dear Hall-D Friends,

   The current accelerator schedule has changed little today except that the white board
indicates beam for Physics is not expected before day shift on Sat. April 11th. As such:

ALL HALL-D SHIFTS ARE CANCELLED UNTIL DAY SHIFT ON SATURDAY APRIL 11th.

I will send additional updates as they become available.

As I mentioned in the biweekly meeting this morning, I have started drafting a revised Run
Plan based on the original plan for this Spring. You can find it here:

https://halldweb.jlab.org/hdops/wiki/index.php/Spring_2015_6GeV_Commissioning_Plan

Please have a look and send any comments or suggestions to Alexander Deur 
(deurpam at jlab.org) and CC myself (davidl at jlab.org), Eugene (gen at jlab.org), and
Elton (elton at jlab.org).

Regards,
-David Lawrence (acting Run Coordinator)