[Halld] Shifts canceled until next Friday (Apr. 17th)

Alexandre Deur deurpam at jlab.org
Fri Apr 10 08:29:44 EDT 2015


Dear collaborators,

A further delay of a day was announced this morning at the accelerator meeting. This is not due to a specific problem, just that each tasks necessary for the accelerator recovery is taking a bit longer than expected. Shifts are now canceled until Friday morning (April 17th), 8am.

Reminder: Our two next run coordination meetings will be Monday 13th and Wednesday 15th.

Best regards,

Alexandre Deur, Hall D Run Coordinator.
 
RC cell: 757-383-5542
Office Phone: 757-269-7526

----- Original Message -----
> From: "Alexandre Deur" <deurpam at jlab.org>
> To: "halld" <halld at jlab.org>
> Sent: Thursday, April 9, 2015 9:20:43 AM
> Subject: Shifts canceled until next Thursday (Apr. 16th)

> Dear collaborators,
> 
> There is another delay of two days in the restoration of the accelerator. Some
> of the work necessary to reconfigure the cooling system so that one CHL can
> cool both linacs (u-tube work) is delicate. It was decided to allow more time
> for this task so that it can be done as carefully as needed.
> 
> Shifts are now canceled until Thursday morning (April 16th), 8am.
> 
> Our next run coordination meeting will be Monday 13th. Due to additional delay,
> the next day meeting (Tuesday 14th) is cancelled.
> 
> Thank you,
> 
> Alexandre Deur, Hall D Run Coordinator.
>  
> RC cell: 757-383-5542
> Office Phone: 757-269-7526
> 
> ----- Original Message -----
>> From: "Alexandre Deur" <deurpam at jlab.org>
>> To: "halld" <halld at jlab.org>
>> Sent: Wednesday, April 8, 2015 9:59:29 AM
>> Subject: Shifts canceled until next Tuesday (Apr. 14th)
> 
>> Dear collaborators,
>> 
>> There will be another day, possibly two, delay in the repairs of the accelerator
>> cooling system. Shifts are now canceled until Tuesday morning (April
>> 14th), 8am. The run coordination meeting of Friday is cancelled as well. Our
>> next run coordination meeting will be Monday 13th.
>> 
>> Best regards,
>> 
>> Alexandre Deur, Hall D Run Coordinator.
>>  
>> RC cell: 757-383-5542
>> Office Phone: 757-269-7526
>> 
>> 
>> ----- Original Message -----
>>> From: "Alexandre Deur" <deurpam at jlab.org>
>>> To: "halld" <halld at jlab.org>
>>> Sent: Tuesday, April 7, 2015 8:26:53 AM
>>> Subject: Shifts canceled until next Monday (Apr. 13th)
>> 
>>> Dear collaborators,
>>> 
>>> Following up on the accelerator repair/investigations: Some leaking bellows were
>>> found yesterday during the leak checks of the accelerator sub-atmospheric
>>> connections. Their repairs are ongoing and the leak checking is continuing.
>>> This is causing an additional day of delay before the machine is restored to
>>> operations. Consequently, shifts are now canceled until Monday morning (April
>>> 13th), 8am.
>>> 
>>> Thank you,
>>> 
>>> Alexandre Deur, Hall D Run Coordinator.
>>>  
>>> RC cell: 757-383-5542
>>> Office Phone: 757-269-7526
>>> 
>>> ----- Original Message -----
>>>> From: "Alexandre Deur" <deurpam at jlab.org>
>>>> To: "halld" <halld at jlab.org>
>>>> Sent: Monday, April 6, 2015 9:29:25 AM
>>>> Subject: Re: [Halld] Shifts canceled until next Sunday (Apr. 12th)
>>> 
>>>> Dear collaborators,
>>>> 
>>>> Given that the machine will be down until at least Sunday, we will not have our
>>>> regular daily run coordination meetings. We will have only two meetings this
>>>> week, Wednesday and Friday at the usual time, 8:45am. Daily meetings will
>>>> restart next week.
>>>> 
>>>> Best regards,
>>>> 
>>>> Alexandre
>>>> 
>>>> ----- Original Message -----
>>>>> From: "Alexandre Deur" <deurpam at jlab.org>
>>>>> To: "halld" <halld at jlab.org>
>>>>> Sent: Monday, April 6, 2015 9:22:39 AM
>>>>> Subject: [Halld] Shifts canceled until next Sunday (Apr. 12th)
>>>> 
>>>>> Dear collaborators,
>>>>> 
>>>>> Repairs and adaptation of the cooling system to the 6 GeV run is proceeding as
>>>>> expected. A committee has been set-up to investigate the origin of the problems
>>>>> triggered by the power failure, in particular the origin of the contamination
>>>>> found in the cooling system. A recommendation of the committee is to verify the
>>>>> bellows in the North Linac for leaks that could have been at the origin of the
>>>>> contamination. This will be done today. It will postpone the recovery schedule
>>>>> by a day. Consequently, shifts are canceled until Sunday morning (April 12th),
>>>>> 8am.
>>>>> 
>>>>> Best regards,
>>>>> 
>>>>> Alexandre Deur, Hall D Run Coordinator.
>>>>>    
>>>>> RC cell: 757-383-5542
>>>>> Office Phone: 757-269-7526
>>>>> _______________________________________________
>>>>> Halld mailing list
>>>>> Halld at jlab.org
> > > > > https://mailman.jlab.org/mailman/listinfo/halld


More information about the Halld mailing list