Folks,
Accelerator continues to work on machine recovery. Re-establishing
vacuum after warm-up of some CHL components is in progress. No major
leak has been found, though the suspicion of its existence remains.
There is an option being considered to run the machine even without leak
discovery if that can be done safely and get us to mid-April. A decision
on that option will be made on Sunday.
The nominal schedule has not changed, both for the machine and for our
shifts. As such, shifts remain on standby for Tuesday and Wednesday,
March 22 and 23.