Dear Collaborators,
Accelerator repairs continue to be on track. Consequently, we are planning to ramp-up the solenoid tomorrow and cool the LH2 target. While the magnet ramps up, the hall will be swept and put in controlled access.
The shifts are cancelled until Friday morning (03/23, 8am), for the same reason as yesterday (please see below).
Please let me or Ben. Zihlmann know if you need more information.
Best regards,
Alexandre Deur, Hall D Run Coordinator.
RC cell: 757-383-5542
Office Phone: 757-269-7526
----- Original Message -----
> From: "Alexandre Deur" <deurpam at jlab.org>
> To: "gluex-collaboration" <gluex-collaboration at jlab.org>, "halld" <halld at jlab.org>
> Sent: Tuesday, March 20, 2018 6:54:12 PM
> Subject: Shift status
> Dear Collaborators,
>
> Accelerator is perfectly on schedule with the CHL transformer repair. This
> removes some of initial uncertainties in the schedule and standby shifts are
> canceled up to Thursday 22nd, 8am. Please contact me (RC) or Ben. Zihlmann
> (PDL) if you need more information.
>
> Best regards,
>
> Alexandre Deur, Hall D Run Coordinator.
>
> RC cell: 757-383-5542
> Office Phone: 757-269-7526