Hello everyone,

Here are the current plans for the rest of the running period:
    -Tonight, we will be able to continue with the High Intensity Scan. I spoke with the PD and told him the +/- 40 nA fluctuation on the beam current will not affect our studies. He said, if that was the case, they would have no problem sending us beam.
    -Tomorrow is going to be the Wien angle change. This will happen no earlier than 8:00 am. It will be requested to be at -50 degrees, and there will be no other change for the rest of the running period.
          -MCC needs to do a study on the harp scan. The estimated time of the study is 2hr. This is currently unscheduled, but it will be discussed at the 1:30 pm meeting.
    -We will tentatively do a TAC run on Monday.
    -On Tuesday, during the Day shift, we will ramp down the magnet to prepare for the straight track and Campton runs

Best regards,

Edmundo S. Barriga
RC
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld/attachments/20250827/43daec5a/attachment.htm>


More information about the Halld mailing list