<div dir="ltr">Dear Collaborators,<div><br></div><div>Here is a brief summary of progress last week (Nov 1-7):</div><div><br></div><div>We were scheduled to receive 161 hours of beam and received 104, with 98 of those acceptable.  The largest period of downtime was caused by a vacuum pump failing in the photon beamline in the tagger hall.  It has been replaced.  </div><div><br></div><div>Special tasks completed during the week include:</div><div><br></div><div>CompCal installation continued during scheduled downtimes, controls were tested and nitrogen flow connected;<br></div><div>Test run with coherent Bremsstrahlung peak at 7GeV instead of the usual 9GeV, and low beam current, in preparation for low photon energy studies;</div><div>Test run with the Pair Spectrometer at half its usual field, also in preparation for low photon energy studies;</div><div>TAC run with low Pair Spectrometer field setting was in progress on Wednesday when my week as RC ended. </div><div><br></div><div>During the week we collected a total of 12.7 E9 production triggers.</div><div><br></div><div>Best regards,</div><div><br></div><div>Naomi.</div></div>