Hi,
Thanks. I assume the target people know about the move to only C in the solid target?
Or
--
Or Hen,
Massachusetts institute of Technology,
Cambridge, MA 02139, USA.
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.hen-2Dlab.com&d=DwIFAg&c=CJqEzB1piLOyyvZjb8YUQw&r=66Sb4pp0d4diwFuNQ_jTiKyZDsB_FG2X3Hlmk9_wuSY&m=AaQZdNRfnDHXGweCpx24mFWfI5G2QUjChbVy-4J2G4A&s=tyXFQ1_CVPfxoM76o6vwhioorUuo60vNxfnIpt-kAes&e= <https://urldefense.proofpoint.com/v2/url?u=http-3A__www.hen-2Dlab.com_&d=DwIFAg&c=CJqEzB1piLOyyvZjb8YUQw&r=66Sb4pp0d4diwFuNQ_jTiKyZDsB_FG2X3Hlmk9_wuSY&m=AaQZdNRfnDHXGweCpx24mFWfI5G2QUjChbVy-4J2G4A&s=eRIvqVmdkLzW24Y0BcgNVjLdncaHVwkAPrAOPmehjCg&e= >
On Oct 5, 2021, at 12:57 PM, Holly Szumila-Vance <hszumila at jlab.org<mailto:hszumila at jlab.org>> wrote:
Dear all,
Here is the updated run plan we can start with as discussed from today:
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1mJQTz5b4-5FHL-5FRNFRoc7gC2DBMOICDmvOxjHiTIT3ZWw_edit-3Fusp-3Dsharing&d=DwIFAg&c=CJqEzB1piLOyyvZjb8YUQw&r=66Sb4pp0d4diwFuNQ_jTiKyZDsB_FG2X3Hlmk9_wuSY&m=AaQZdNRfnDHXGweCpx24mFWfI5G2QUjChbVy-4J2G4A&s=fyZW8PVALSEusP3S1Qk0jmgZQ7l6mCro-xpWZDQA1dY&e=
The summary is as follows:
12 days on 4He
2 days on D
9 days on C
Overhead (needs to be detailed): 2 shifts detector and DAQ checkout, 2 shifts Compton, 2 shifts empty cell setup/running, 3 shifts 4He->D, 5 shifts D->C
Estimated rates attached.
-Holly
<Screen Shot 2021-10-05 at 12.54.54 PM.png>_______________________________________________
halld_src mailing list
halld_src at jlab.org<mailto:halld_src at jlab.org>
https://mailman.jlab.org/mailman/listinfo/halld_src
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/halld_src/attachments/20211010/2b3353b0/attachment-0001.html>
More information about the halld_src
mailing list