[Hdicecontrols] DSG HDice Work Status
Peter Bonneau
bonneau at jlab.org
Thu Aug 11 14:45:07 EDT 2016
Hello,
DSG completed the HDice work requests that are under our control three
weeks ago.
We are ready to install, test, and debug the equipment for the 2nd NRM
rack in the HDice lab, but an OSP is needed for this work.
We heard an OSP was being written about a month ago. Let us know when a
OSP for this work has been approved.