Hi,
the status of the LED boards is the following:

- 1 driver will be delivered next week. As soon as I get the driver,
I'll test it, to check that the modifications we implemented are fine.
If so, the other drivers will be mounted (PCB have been already
produced, but the components have not yet been soldered).
- I am waiting for the status of the connection board. The order was
placed some time ago (~ weeks).
- I am waiting also for the status of the controllers. The manufacturing
company will tell me something tomorrow.


Unfortunately, it seems that Easter holidays delayed the production..

As requested by John, I am giving an update of the LED system on Wednesday.
I was planning to show and discuss the slides today at the Ecal meeting,
so please find them attached (still in a preliminary form)
I can implement comments and suggestions before Wednesday, 2PM, Europe
time (8 AM JLab time).

In particular, there are two points that are important to discuss among us:

- The expected dose rate for the ECAL (EM and neutrons), that is
important to estimate if there is any radiation damage to the LEDs.
Here I do not have any guess.

  - The way the LED system will be used during commissioning and during
the run. I wrote some ideas in the slides, please look them and see if they look reasonable.

Regards

Andrea

Il 04/28/2014 03:35 PM, dupre ha scritto:
> Hello everyone,
>
> I am not in Orsay those days and my laptop does not seem to like
> readytalk very much so we will have to postpone today's meeting.
>
> If people can give some short progress report by e-mail it would be
> perfect. Gabriel can you give an update on work in Orsay? Marco or
> Andrea could you tell us if the orders for the different boards have
> been delivered?  And Michel or Holly could you give some information on
> the gluing and APD testing progress?
>
> Stepan also reminds me that we also need to prepare for the readiness
> review from JLab that will be held early July. For this review we should
> provide an operation manual including calibration procedures! I hope we
> can get at the collaboration meeting with a descent draft!
>
> Best regards,
>



-------------- next part --------------
A non-text attachment was scrubbed...
Name: Celentano-LedMonitor.pdf
Type: application/x-filler
Size: 2757221 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/hps-ecal/attachments/20140428/5472a1e8/attachment-0001.bin 


More information about the Hps-ecal mailing list