This is a reminder of what has been discussed during last meeting.
The calorimeter support structure will be installed in the hall during
the week of Sept. 29. The expert for this is E. Rindel, he already
booked is plane and will be in JLab for the full week with Gabriel.
Before that, in the coming weeks, JLab people will prepare the cabling
for the ECal (HV, LV, LED system and signal), install the FADCs and the
LED controller in the right crates, work on the rails parallelism and
bring the ECal modules and the chiller in the alcove. It would also be
good to have the scintillators for cosmics ready so they can be
installed on the structure at the same time than the ECal.
After that, from October 6 to 17 commissioning of the Calorimeter with
LED system and cosmics will take place. People needed are a LED system
expert and a DAQ expert so that we can have these things go forward
rapidly. It would be good to confirm the presence and availability of
experts at these dates. Marco, tell us when you know who can come and
when. Stepan, it would be good to check that people from DAQ will be
available these weeks.