Dear Everyone,
Next week the accelerator will work to resume multi-hall operation, and
it is possible Hall-B will have beam as early as Thursday evening.
So, shifts in the Hall-B counting room are set to resume on Thursday,
December 4 with the swing shifts.
The previously planned down time Dec. 5-12 has been cancelled and will
now need to have shifts manned.
The plan is for the HPS target assembly to have been installed and tested
by Wednesday, and the full beamline returned to vacuum and the hall closed
on Thursday. Then take beam to the tagger dump and repeat and finish
quality studies, and then do the same with beam to the Faraday cup.
Regards,
Nathan